Only figures with a source on file. Each carries its own date — programme figures are published at different times, so they are not summed or compared across dates.
Port capacity
Major ports 1,681 MTPA (FY25) · combined 2,818 MTPA (Mar 2026) [12][8]As of 24 Jul 2026
Completed315 projects · ₹1.57 lakh crore (~26% of portfolio value)24 Mar 2026 [4]
Operational
—
02 · Why it mattersTechadyant analysis
How Sagarmala is changing India’s industrial system
Interpretation, labelled. Sourced statements are marked Fact.
Analysis Sagarmala is less about ports than about where industry sits relative to them. Its distinctive pillar is port-led industrialisation: putting processing next to the gateway so that a land leg disappears from the supply chain.
Fact By project count the programme is well advanced — 315 of 845 projects completed. By value it is not: completed projects account for ₹1.57 of ₹6.06 lakh crore, about a quarter (24 Mar 2026). [4]
Analysis That gap suggests the large-ticket items — new ports and industrial zones — are the ones still to come. Those are the items that would change industrial geography.
03 · Geographic footprintDerived from the graph
Where Sagarmala meets India’s industrial geography
Shows only industrial nodes and infrastructure reached through an evidenced project link, not the programme’s full national network. Techadyant does not replicate PM GatiShakti’s GIS. National footprint: coastline, major and non-major ports, coastal states/uts and national waterways. Ports are the Sagarmala registry (major, non-major, under construction), plus minor ports named on Sagarmala’s “String of Ports” slide that the registry does not yet hold. Freight and industrial corridors are context lines for the port-connectivity pillar, not Sagarmala-funded assets. Ports without recorded coordinates sit at town level.
seaport · Gujarat
Deendayal (Kandla)
operational
Major port · Authority: Deendayal Port Authority (MoPSW) · FY 2025-26 throughput 160.11 MT · rank 1 among major ports. Documented connections: Road over bridge at LC-235 (road, approved).
Schematic. Positions are approximate centroids; distances on dossiers are straight-line and labelled as such.
04 · Programme componentsFact
How the programme is built
Expand a component for its scope and the latest sourced progress.
Port modernisation & new port developmentUnder implementation
Capacity, mechanisation and new ports.
Progress: Seven coastal-berth projects (₹494 crore) added 9.84 MTPA; Vadhavan (₹76,220 crore, 298 MTPA planned) under construction after the June 2024 Cabinet approval; Vizhinjam Phase 1 operational since 3 December 2024 and past 1 M TEU in its first year.
Road, rail and other links between ports and hinterland.
Progress: Comprehensive Port Connectivity Plan: 294 rail/road projects identified — 84 completed, 66 under implementation, 144 under planning (Jul 2026); e.g. ₹132.51 crore road over bridge at Deendayal Port approved (Apr 2026).
Industrial clusters and Coastal Economic Zones near ports.
Progress: Perspective plans prepared for all 14 CEZs; no project sanctioned for financial assistance under this pillar of the Sagarmala scheme (Rajya Sabha reply, 11 Aug 2026).
Two scopes, never summed: the programme portfolio (all funding modes) and the scheme-funded projects (MoPSW financial assistance). Each snapshot carries its own date — portfolio figures published at different times are not compared across dates.
Scheme-funded projects by pillar as of 24 Jul 2026 · Lok Sabha reply
Pillar
Completed
Completed cost
Under impl.
UI cost
Portfolio split (Mar 2025)
E · Coastal shipping & IWT
25
₹1,178.5 cr
17
₹1,167.7 cr
231 projects · ₹14,526 cr
D · Coastal community development
19
₹1,912.6 cr
28
₹3,008.4 cr
81 projects · ₹11,573 cr
A · Port modernisation & new ports
18
₹870.2 cr
6
₹160.8 cr
234 projects · ₹2,91,622 cr
B · Port connectivity
17
₹1,413.2 cr
3
₹201.3 cr
279 projects · ₹2,06,363 cr
C · Port-led industrialisation
0
—
0
—
14 projects · ₹55,887 cr identified
Scheme-funded total
79
₹5,374.5 cr
54
₹4,538.2 cr
845 projects · ₹6.06 lakh crore (portfolio, Mar 2026)
Fact No row exists for port-led industrialisation: no project has been sanctioned for financial assistance under that pillar of the Sagarmala scheme (confirmed separately on 11 Aug 2026). [8][9] Scheme lifecycle: 186 sanctioned · 58 withdrawn · 128 funded (78 completed, 50 under implementation) as of 13 Feb 2026. [10]
Flagship project explorer 13 documented projects · search and filter
13 of 13 projects
Project
Pillar
Location
Status
Cost
Agency
Vadhavan Port (greenfield major port, artificial island)
A · Port modernisation & new ports
Vadhavan, Dahanu, Palghar district, Maharashtra
under construction
₹76,220 cr
Vadhavan Port Project Ltd (VPPL) — SPV of Jawaharlal Nehru Port Authority (74%) and Maharashtra Maritime Board (26%); VPPL incorporated 14 September 2016
Vizhinjam International Seaport, Phase 1 (deepwater transshipment port)
A · Port modernisation & new ports
Vizhinjam, Thiruvananthapuram, Kerala
operational
₹8,867 cr
Vizhinjam International Seaport Ltd (Kerala government) with Adani Ports & SEZ as concessionaire
Road over bridge at level crossing LC-235, Deendayal Portscheme
B · Port connectivity
Kandla, Gujarat
approved
₹132.51 cr
Deendayal Port Authority
Obulavaripalle–Venkatachalam (Krishnapatnam) new rail line
B · Port connectivity
Andhra Pradesh (Nellore district)
completed
—
Krishnapatnam Railway Company Ltd (KRCL) with Sagarmala Development Company Ltd equity
Haridaspur–Paradip rail line and doubling
B · Port connectivity
Odisha (Jajpur–Paradip)
under constructionNew line completed; doubling under implementation per the February 2026 Odisha connectivity reply.
₹2,542 cr
Haridaspur Paradip Railway Company Ltd (HPRCL) with Sagarmala Development Company Ltd equity (₹33.68 crore = 25.91%)
National Waterway 1 (Ganga: Haldia–Varanasi, 1,390 km)
completed
₹5,369.18 cr
Inland Waterways Authority of India
NW-2, NW-3 and NW-4 terminal programme
E · Coastal shipping & IWT
Brahmaputra (NW-2), West Coast Canal Kerala (NW-3), Kakinada–Puducherry canals/Godavari (NW-4)
completed
—
Inland Waterways Authority of India
NW-5 Phase-1 (Talcher–Dhamra–Paradip–Pankapal)
E · Coastal shipping & IWT
Odisha (Brahmani–Mahanadi system)
under construction
—
Inland Waterways Authority of India
Ghogha–Hazira Ro-Pax ferry servicescheme
E · Coastal shipping & IWT
Gulf of Khambhat, Gujarat
operationalHazira Ro-Pax facility completed in CY2023; vessels have moved ~36,000 trucks, 61,000 cars and ~4 lakh passengers.
—
Gujarat Maritime Board with MoPSW support
Coastal berth programmescheme
A · Port modernisation & new ports
Multiple states (Visakhapatnam, JNPT, Kollam, Old Mangaluru, VOCPT among others)
partially operationalSeven berths completed; more sanctioned in the 128-project scheme list (Visakhapatnam coastal berth completed 30/09/2017 at ₹43 crore; JNPT, Kollam, Old Mangaluru and VOCPT berths in the list).
₹494 cr
Respective port authorities with MoPSW financial assistance
Fishing harbour and fish landing centre programmescheme
D · Coastal community development
Multiple coastal states (Malpe and Kulai in Karnataka; Juvvaladinne and Visakhapatnam in AP; Chennai, Mookaiyur, Kunthukal, Poompuhar and Chinnamuttom in Tamil Nadu; Cochin, Thalai, Chettuva and Chellanam in Kerala; Sassoon Dock, Mallet Bunder, Karanja, Anandwadi, Mirkawada in Maharashtra; Mangrol in Gujarat; Paradip and Chandipur in Odisha)
partially operational11 completed; several others under implementation in the 128-project scheme list.
₹1,057 cr
Port authorities, state maritime boards and state fisheries departments
Centre of Excellence in Maritime and Shipbuilding (CEMS)scheme
D · Coastal community development
Visakhapatnam (Andhra Pradesh) and Mumbai (Maharashtra)
operational
₹574 cr
Indian Register of Shipping with MoPSW support
Lighthouse tourism programme
D · Coastal community development
Nationwide (Directorate General of Lighthouses and Lightships)
operational75 lighthouses operational as tourist attractions.
—
Directorate General of Lighthouses and Lightships (MoPSW)
A · Port modernisation & new ports
Vadhavan Port (greenfield major port, artificial island)
Location
Vadhavan, Dahanu, Palghar district, Maharashtra
Status
under construction
Cost
₹76,220 cr
Agency
Vadhavan Port Project Ltd (VPPL) — SPV of Jawaharlal Nehru Port Authority (74%) and Maharashtra Maritime Board (26%); VPPL incorporated 14 September 2016
Planned capacity
298 MTPA
All-weather greenfield deep-draft major port built on an artificial island off Vadhavan; natural depth of ~20 m available at 10 km; harbour designed for container ships up to 233,000 DWT; landlord-port model.
Notified as a Major Port in the Government Gazette. [44]
Union Cabinet approves development at ₹76,220 crore. [25]
₹5,301 crore breakwater contract awarded to Afcons. [69]
Analysis Designed as India's first offshore port; the deepest-draft capacity addition of the programme, aimed at ultra-large container vessels that currently bypass Indian gateways.
Vizhinjam International Seaport, Phase 1 (deepwater transshipment port)
Location
Vizhinjam, Thiruvananthapuram, Kerala
Status
operational
Cost
₹8,867 cr
Agency
Vizhinjam International Seaport Ltd (Kerala government) with Adani Ports & SEZ as concessionaire
Planned capacity
1 M TEU (Phase 1 design)
India's first dedicated deepwater container transshipment port; natural depth ~24 m; Kerala-owned, Adani-operated under a 40-year concession; designed to accommodate ~50% of India's container transshipment currently handled at Dubai, Colombo and Singapore.
First cargo vessel (Zhen Hua 15, crane carrier) docks. [82]
First container ship (San Fernando) on trial run; limited-scale operations begin. [82]
Commercial operations of Phase 1 commence with a designed capacity of 1 million TEUs. [4]
MSC Türkiye (24,346 TEU) calls — largest vessel handled to date. [82]
Port dedicated by the Prime Minister (~₹8,800 crore). [82]
Analysis Keeps Indian-bound transshipment cargo in Indian terminals instead of Colombo/Dubai/Singapore; anchor for a port-adjacent services economy in Thiruvananthapuram.
Throughput keeps its reporting period and source: FY 2024-25 is final Basic Port Statistics; FY 2025-26 is the advance estimate. Port-level totals never include terminal-level figures. A missing Sagarmala project link means no documented project on file, not absence of relevance.
Port
State
Type
FY 2024-25
FY 2025-26 (adv.)
Sagarmala projects
Deendayal Port Authority (Kandla)FY26 rank #1
Gujarat
Major port
150.157 MT
160.11 MT
Road over bridge at level crossing LC-235, Deendayal Port
Paradip Port AuthorityFY26 rank #2
Odisha
Major port
150.408 MT
156.451 MT
Haridaspur–Paradip rail line and doublingNW-5 Phase-1 (Talcher–Dhamra–Paradip–Pankapal)
Jawaharlal Nehru Port Authority (JNPA, Nhava Sheva)FY26 rank #3
V.O. Chidambaranar Port Authority (Tuticorin)FY26 rank #10
Tamil Nadu
Major port
41.724 MT
43.21 MT
—
Cochin Port AuthorityFY26 rank #11
Kerala
Major port
37.745 MT
38.063 MT
—
Mormugao Port AuthorityFY26 rank #12
Goa
Major port
18.126 MT
20.837 MT
—
Vadhavan Port (under construction)
Maharashtra
Major port (under construction)
—
—
Vadhavan Port (greenfield major port, artificial island)
Galathea Bay Port, Great Nicobar (under construction)
Andaman & Nicobar Islands
Major port (under construction)
—
—
—
Mundra Port (Gujarat Adani Port)
Gujarat
Non-major port
199.54 MT
—
—
Sikka Port and Terminals
Gujarat
Non-major port
136.24 MT
—
—
Krishnapatnam Port
Andhra Pradesh
Non-major port
54.99 MT
—
Obulavaripalle–Venkatachalam (Krishnapatnam) new rail line
Dhamra Port
Odisha
Non-major port
46.08 MT
—
NW-5 Phase-1 (Talcher–Dhamra–Paradip–Pankapal)
Dahej Port
Gujarat
Non-major port
36.08 MT
—
—
Magdalla Port
Gujarat
Non-major port
35 MT
—
—
Dharamtar Port
Maharashtra
Non-major port
28.24 MT
—
—
Gangavaram Port
Andhra Pradesh
Non-major port
26.97 MT
—
—
Kakinada Deep Water Port
Andhra Pradesh
Non-major port
17.81 MT
—
—
Pipavav Port (Gujarat Pipavav Port Ltd)
Gujarat
Non-major port
13.93 MT
—
—
Kattupalli Port
Tamil Nadu
Non-major port
11.48 MT
—
—
Vizhinjam International Seaport
Kerala
Non-major port
—
—
Vizhinjam International Seaport, Phase 1 (deepwater transshipment port)
Jaigarh Port (JSW Jaigarh Port Ltd)
Maharashtra
Non-major port
—
—
—
Gopalpur Port
Odisha
Non-major port
6 MT
—
—
Fact 217 notified non-major ports across the coastal states and UTs; 69 under 11 state maritime boards/directorates report on the Port Data Monitoring Platform. Non-major ports handled 742.41 MT in FY 2024-25 (747.71 MT provisional alternative) and 753.07 MMT in FY 2025-26 (advance). Gujarat alone accounted for 487.73 MT (65.70%) in FY25. All-ports (major + non-major) throughput was 1,597.27 MT in FY25 — major ports 53.52%. [25][27]
07 · Port performance trendsFact
What the throughput record shows
Annual series with a source on every point. Incompatible series (financial-year vs calendar, PIB narrative vs revised BPS definition) are kept separate — never combined into one trend.
12 major ports (annual, financial year)total cargo handled · MT
Fact Nine Indian ports feature in the world top-100; Visakhapatnam is in the top-20 for container traffic (April 2026 PIB feature). JNPA is ranked 22nd in the World Bank Container Port Performance Index 2025. [4][13]
Fact Sagar Aankalan / LPPI FY 2024-25: 12 major and 35 non-major port terminals participated; the container category was led by Mundra with JNPA second. [32]
08 · Port-led industrialisationFact
Fourteen zones, zero sanctioned projects
The Atlas’s differentiator pillar. The status is verified, not assumed: proposed zones are never described as operating clusters.
Fact No project has been sanctioned for financial assistance under the port-led industrialisation pillar of the Sagarmala scheme (Rajya Sabha reply, 11 August 2026); consistent with the absence of an industrialisation row in the July 2026 pillar-wise annexure. The 14 CEZ projects (₹55,887 crore) counted in the 839-project portfolio split are identified projects, not scheme-funded ones. [9][8]
Coastal Economic Zone
State
Linkage ports
Intended sectors
Status
CEZ-1 Gujarat (Kandla–Mundra)
Gujarat
Deendayal Port Authority (Kandla) · Mundra Port (Gujarat Adani Port)
Petrochemicals · Cement · Furniture
proposed
CEZ-2 Gujarat (Pipavav–Sikka)
Gujarat
Pipavav Port (Gujarat Pipavav Port Ltd) · Sikka Port and Terminals
Apparel · Automotive
proposed
CEZ-3 Gujarat (Dahej–Hazira)
Gujarat
Dahej Port
Marine clusters
proposed
CEZ-4 Maharashtra/Goa (JNPT–Mumbai)
Maharashtra
Jawaharlal Nehru Port Authority (JNPA, Nhava Sheva) · Mumbai Port Authority
Power · Electronics · Apparel
proposed
CEZ-5 Maharashtra/Goa (Dighi–Jaigarh–Mormugao)
Maharashtra
Jaigarh Port (JSW Jaigarh Port Ltd) · Mormugao Port Authority
Refining · Steel · Food processing
proposed
CEZ-6 Karnataka (New Mangalore)
Karnataka
New Mangalore Port Authority
Petrochemicals
proposed
CEZ-7 Kerala (Cochin)
Kerala
Cochin Port Authority
Furniture
proposed
CEZ-8 Tamil Nadu (VOCPT Tuticorin)
Tamil Nadu
V.O. Chidambaranar Port Authority (Tuticorin)
Apparel · Refining
proposed
CEZ-9 Karaikal
Puducherry
—
Leather processing · Power
proposed
CEZ-10 Tamil Nadu (Chennai–Kamarajar/Ennore–Kattupalli)
Tamil Nadu
Chennai Port Authority · Kamarajar Port Ltd (Ennore) · Kattupalli Port
Syama Prasad Mookerjee Port Authority, Kolkata (KDS + Haldia) · Haldia Dock Complex (part of SMP Kolkata)
Leather processing
proposed
Fact Each CEZ consists of multiple Coastal Economic Units (CEUs), and more than one industrial cluster can be housed within a CEZ. To accelerate CEU development, locations like Kandla, Paradip, Ennore and Vizag were proposed as priorities where land parcels are available close to a deep-draught port with strong manufacturing potential. CEZs are spatial economic regions spread over multiple coastal districts with strong port linkage. [23]
Analysis The geography the CEZs were meant to capture already exists in partial form: petrochemicals at Dahej and Sikka, refining-steel at the Maharashtra coast, electronics at Sriperumbudur and Kopparthy served by Chennai/Kamarajar and Krishnapatnam. What the pillar has not delivered is the dedicated zone instrument — the land, utilities and single-window apparatus that would pull import-heavy processing to the waterfront.
Analysis If CEZs move to notified land, import-heavy processing (energy, chemicals, metals) is the most likely early mover. None is documented as a CEZ unit on file.
09 · Coastal community developmentFact
The human dimension, reported not inferred
Beneficiary counts are ministry-reported outputs with their dates — not independently measured outcomes, and never a basis for inferred income effects.
Only relationships a source documents (operator, concession, acquisition, contract, fleet). No company here is claimed to be an official Sagarmala partner or beneficiary — that claim needs evidence for the precise relationship.
Port operators2 companies
Adani Ports and SEZ Ltd (APSEZ)
operates → Mundra Port (Gujarat Adani Port)Flagship port with four container terminals (combined 7.5 M TEU capacity); ~199.54 MT FY25. [50][25]
acquired → Krishnapatnam Port75% in October 2020 (EV ₹13,675 crore), raised to 100% by acquiring Vishwasamudra Holdings' 25% for ₹2,800 crore. [50][84]
acquired → Gangavaram Port31.5% from Warburg Pincus (₹1,954 crore, March 2021), Raju family stake (₹3,604 crore), remaining 58.1% in 2022 (~₹6,200 crore deal value) — 100% ownership. [51][79]
acquired → Gopalpur Port₹3,500 crore acquisition, March 2024. [84]
concession → Vizhinjam International SeaportSole-bidder 40-year operating concession (2015), ~₹6,000 crore superstructure; Phase 1 operations from 3 December 2024. [52][82]
operates → Kattupalli PortContainer terminal operated by Adani Kattupalli Port under authorisation from L&T Shipbuilding (port owner). [81]
concession → Kamarajar Port Ltd (Ennore)Adani Ennore Container Terminal — concession agreement 1 March 2014, ₹1,270 crore; operations from 19 March 2018. [42]
operates → Dhamra PortDhamra Port within the Adani portfolio; 46.08 MT FY25. [50][25]
JSW Infrastructure Ltd
operates → Jaigarh Port (JSW Jaigarh Port Ltd)JSW Jaigarh Port — the group's Ratnagiri deep-water port. [60]
operates → Paradip Port AuthorityParadip East Quay Coal Terminal. [60]
operates → Kamarajar Port Ltd (Ennore)Ennore coal/bulk terminals. [60]
operates → New Mangalore Port AuthorityMangalore coal and container terminals. [60]
Terminal operators6 companies
DP World
operates → Jawaharlal Nehru Port Authority (JNPA, Nhava Sheva)NSICT — 30-year concession from 1997, India's first port PPP; re-award process underway 2025-26 after tariff-dispute settlement (April 2025). [53]
operates → Jawaharlal Nehru Port Authority (JNPA, Nhava Sheva)NSIGT — Nhava Sheva India Gateway Terminal. [53]
concession → Cochin Port AuthorityVallarpadam International Container Transshipment Terminal — 30-year concession, reverting to Cochin Port thereafter; Zodiac terminal operating system. [53]
PSA International (PSA India)
operates → Chennai Port AuthorityCITPL — licensed 2007, full ownership of the port's second container terminal from 2010; three berths across an 832-metre quay. [54]
operates → Jawaharlal Nehru Port Authority (JNPA, Nhava Sheva)BMCT — JNPA's fourth container terminal; 4.8 M TEU capacity, 2,000 m quay; 2.6 M TEUs handled in CY2025. [55]
exited → V.O. Chidambaranar Port Authority (Tuticorin)PSA SICAL container terminal (JV formed December 1999); PSA wound up operations and exited the concession early in March 2025. [56][57]
APM Terminals (A.P. Moller–Maersk)
operates → Pipavav Port (Gujarat Pipavav Port Ltd)Majority shareholder and operator of Gujarat Pipavav Port Ltd; MoU with Gujarat Maritime Board for a ~US$2 billion expansion (30 October 2025). [58][59]
operates → Jawaharlal Nehru Port Authority (JNPA, Nhava Sheva)GTI — 74:26 JV with Container Corporation of India, inaugurated January 2007; US$115 million investment announced February 2022. [58]
concession → Jawaharlal Nehru Port Authority (JNPA, Nhava Sheva)NSFT concession signed 29 July with JNPA (J.M. Baxi & CMA Terminals joint venture). [43]
Chettinad International Bulk Terminal Pvt Ltd (CIBTPL)
concession → Kamarajar Port Ltd (Ennore)Multi-cargo terminal concession agreement signed 28 March 2014. [42]
Indian Oil LNG Pvt Ltd (SPV)
concession → Kamarajar Port Ltd (Ennore)LNG terminal concession agreement signed 31 July 2015; construction commenced August 2015. [42]
Shipping lines2 companies
Shipping Corporation of India Ltd (SCI)
supports → Centre of Excellence in Maritime and Shipbuilding (CEMS)Supported creation of 96 training berths on MV Swaraj Dweep with the A&N Administration. [22]
Fleet: 58 vessels · 2.94 M GT
The Great Eastern Shipping Co Ltd
Fleet: 44 vessels · 1.97 M GT
Coastal operators1 company
Shreyas Shipping & Logistics Ltd
Fleet: 17 vessels
Shipyards & ship repair5 companies
Cochin Shipyard Ltd (CSL)
co-located with → Cochin Port Authority₹1,800 crore new dry dock (15 acres, capable of aircraft carriers); land lease with Cochin Port Authority for a new shipbuilding facility (February 2025). [62]
Garden Reach Shipbuilders & Engineers Ltd (GRSE)
co-located with → Syama Prasad Mookerjee Port Authority, Kolkata (KDS + Haldia)Defence shipbuilder on the Hooghly; contract for two Coastal Research Vessels signed 11 June 2025; naval orderbook. [64]
Hindustan Shipyard Ltd (HSL)
co-located with → Visakhapatnam Port AuthorityIndia's first 44,000-tonne Fleet Support Ship project; order book growth from ~₹2,000 crore to ₹20,000+ crore in about three years. [65]
Goa Shipyard Ltd (GSL)
co-located with → Mormugao Port AuthorityMine Counter Measure Vessel collaboration for the Indian Navy. [66]
L&T Shipbuilding (Kattupalli)
owns → Kattupalli PortBuilt and owns Kattupalli port-shipyard complex; INS Samarthak multi-purpose vessel delivered 1 September 2026; part-construction of two Fleet Support Ships; US Navy ship-repair agreements. [67][81]
Dredging4 companies
Dredging Corporation of India (DCI)
ownership → Visakhapatnam Port AuthorityGoI approved transfer of DCI to four government-owned major ports — Visakhapatnam, Paradip, JNPT and Kandla (Cabinet approval 8 November 2018). [68]
ITD Cementation with DEME and Jan De Nul (dredging JV)
contract → Vadhavan Port (greenfield major port, artificial island)Letter of award for Vadhavan dredging and land reclamation (March 2025); DEME share valued at up to €50 million. [83]
Van Oord
contract → Mumbai Port AuthorityMumbai Port maintenance-dredging contract (September 2013); Kandla navigation-channel dredging (2008). [73]
Jan De Nul
contract → Mumbai Port Authority€250 million JV dredging contract covering the 35.5 km Mumbai access channel, turning basins and anchorages (April 2017). [74]
Marine EPC1 company
Afcons Infrastructure Ltd
contract → Vadhavan Port (greenfield major port, artificial island)₹5,301 crore EPC for the 10.14 km breakwater at Vadhavan Port (June 2026) — described as the second-longest breakwater in the world when completed. [69]
Equipment suppliers2 companies
Shanghai Zhenhua Heavy Industries (ZPMC)
supply → Vizhinjam International Seaport24 RMG cranes (10 double-cantilever + 14 single-cantilever) plus quay cranes for the Adani terminal; third shipment on 5 January 2024. [70]
supply → Mundra Port (Gujarat Adani Port)Quay-crane and RMG projects reported in the 2024 ZPMC shipment timeline. [70]
Konecranes
supply → Mundra Port (Gujarat Adani Port)Order for 30 E-Hybrid RTGs booked Q3 2025 for an unnamed Indian greenfield container terminal (delivery Q1 2027) — the terminal is not identified in the source; recorded as a demand signal, not a specific port relationship. [71]
Waterway operators1 company
Inland Waterways Authority of India (IWAI)
implements → Jal Marg Vikas Project — NW-1 multimodal terminalsBuilt and operates the NW-1 terminal chain — Varanasi MMT (1.26 MTPA), Kalughat intermodal terminal (77,000 TEU/yr), Sahibganj MMT; ran India's first container movement on inland waterways (PepsiCo containers, MV RN Tagore, October 2018). [40][41]
implements → NW-2, NW-3 and NW-4 terminal programmeTerminal programmes on NW-2, NW-3 and NW-4, including Ro-Ro services. [40]
11 · Connected industrial nodesDerived from the graph
Industrial nodes affected
Each card shows the evidence path from programme to node. A node appears only when a sourced project links them; two locations being close is not enough.
ProjectRoad over bridge at LC-235, Deendayal Port (Kandla)InfrastructureDeendayal Port (Kandla)RelationshipSanand — gateway port — Deendayal Port (Kandla)
Industrial nodeSanand
India’s first working chip-packaging cluster just gained a dedicated freight-rail station — the connectivity now runs ahead of the supplier base.
12 · Connected logistics systemDerived from the graph
The connected logistics system
Road → rail → DFC → logistics parks → ports → air cargo → industrial nodes. Filled only from records linked to this programme (Atlas projects and the SID logistics layer). An empty row means no linked record yet, not that nothing exists.
Road
No linked record
Rail
No linked record
Dedicated freight corridor
No linked record
Logistics parks & terminals
No linked record
Ports
Deendayal Port (Kandla)operational · via Road over bridge at LC-235, Deendayal Port (Kandla)Vadhavan Port (under construction, Maharashtra)under construction · linked projectVizhinjam International Seaport (Kerala)operational · linked projectDeendayal Port (Kandla)operational · SID logistics layerJawaharlal Nehru Port Authority (JNPA)operational · SID logistics layerMumbai Portoperational · SID logistics layer
Each statement is tagged Fact (sourced) or Analysis (Techadyant interpretation).
Trade
Gateway throughput and speed are rising
Fact Major ports handled a record 915.17 MT in FY 2025-26, and average vessel turnaround fell to 49.5 hours in 2025 from 96 hours in 2014. [4]
Analysis Faster turnaround lowers the cost of using an Indian gateway rather than transhipping. That matters most for container-heavy manufacturing exports.
Logistics
Hinterland links are funded port by port
Fact A ₹132.51 crore road over bridge at Deendayal Port’s LC-235 crossing was approved under Sagarmala to ease cargo evacuation (Apr 2026). [6]
Analysis Deendayal is the gateway port this Atlas records for the Sanand semiconductor node. Port-gate works like this affect node logistics without ever naming the node.
Manufacturing
Port-led industrialisation is the unbuilt pillar
Fact 14 CEZs are proposed with perspective plans. [5]
Fact 14 CEZs are proposed with perspective plans, and in August 2026 Parliament confirmed that no project has been sanctioned for financial assistance under the port-led industrialisation pillar — the unbuilt-pillar reading is now official. [9]
Supply chains
River and coastal routes add a mode
Fact Inland-waterway cargo grew from 18.10 MT in FY 2013-14 to 145.5 MT in FY 2024-25. [4]
Analysis For bulk inputs, a waterway leg can replace road. Its industrial relevance depends on whether terminals sit near clusters.
Technology
Finance as infrastructure
Fact SDCL was restructured in June 2025 as a maritime-focused NBFC and sanctioned about ₹4,300 crore of loans by Dec 2025. [4]
Analysis A dedicated lender changes who can finance port-linked projects, including private terminals and shipbuilding-adjacent industry.
Imported energy, feedstocks and components arrive through major and non-major ports. Analysis
Manufacturing node
Port-adjacent processing is planned through 14 proposed CEZs. Fact[5]
Freight network
Port-connectivity projects link the port gate to road and rail. Fact[6]
Logistics node
Coastal and inland-waterway terminals add a non-road leg (145.5 MT IWT cargo, FY25). Fact[4]
Port / airport
Major ports: 915.17 MT in FY 2025-26; turnaround 49.5 h (2025). Fact[4]
Market
Export markets — the leg where turnaround and port charges set competitiveness. Analysis
15 · Opportunity surfacesOpportunity surface
Where new opportunity may appear
Analytical hypotheses with a sourced trigger, stated constraints and a confidence label (High / Medium / Emerging). Not forecasts, and not procurement signals.
Opportunity surfaceConfidence: Emerging
Port-adjacent processing in Coastal Economic Zones
Trigger
Sagarmala’s port-led industrialisation pillar proposes 14 Coastal Economic Zones with perspective plans prepared; a Sagarmala 2.0 with ₹3.6 lakh crore of total investment is proposed (Apr 2026). [5][4]
Industrial effect
Import-heavy and export-heavy processing could cut a land leg by locating at the port.
Potential opportunity
Port-adjacent processing, storage and utility services where a CEZ moves from perspective plan to notified land.
Affected sectors
Port-led manufacturing · Energy & chemicals
Constraints
CEZs are proposed; notification, land and incentives are not documented here.
Sagarmala 2.0 is a proposal; its approval and content may change.
Coastal land, environmental clearances and port tariffs decide feasibility case by case.
Triggered by this programme · horizon long · a hypothesis, not a forecast or procurement signal.
Opportunity surfaceConfidence: High
Vadhavan's successive marine-works and equipment waves (2026-2035)
Trigger
The ₹76,220 crore Vadhavan port is under construction: a ₹5,301 crore breakwater EPC awarded to Afcons (June 2026) and a dredging/reclamation letter of award to an ITD Cementation-DEME-Jan De Nul JV (March 2025). [69][83]
Industrial effect
Reclamation and breakwater works precede quay construction, mechanisation and landside packages. Successive procurement waves may pull marine civil works, crane supply and maintenance services toward the Palghar coast. A 10.14 km breakwater and a dredged channel create a recurring maintenance regime beyond the construction phase. Indian EPC share of the largest marine packages is growing but dredging remains foreign-led.
Potential opportunity
Potential demand for follow-on marine works, mechanisation packages, crane integration and long-run maintenance contracts as Vadhavan phases proceed.
Affected sectors
Port construction · Marine equipment
Constraints
Award values concentrate in large international EPCs; mid-size Indian suppliers may need consortium routes
Phase timing depends on reclamation completion
Triggered by this programme · horizon medium · a hypothesis, not a forecast or procurement signal.
Opportunity surfaceConfidence: Medium
Transshipment service economy around Vizhinjam's first million TEUs
Trigger
Vizhinjam Phase 1 commenced commercial operations on 3 December 2024 with a designed capacity of 1 million TEUs and crossed 1 million TEUs in its first year — the fastest pace set by any Indian port; later phases target ~5.7 M TEUs. [4][82]
Industrial effect
Mainline and feeder services can re-slot Indian transshipment cargo that previously moved via Colombo, Dubai and Singapore. Terminal-adjacent services — CFS/ICD operations, trucking, marine supplies — scale with vessel calls. Kerala's service-sector base could capture bunkering, crew changes, repairs and chandling flows that currently accrue abroad. Transshipment cargo is contestable; service-ecosystem depth versus Colombo decides stickiness.
Potential opportunity
Potential demand for feeder operations, CFS/ICD capacity, marine services and ship-support industries around Thiruvananthapuram as phases expand.
Affected sectors
Container shipping · Marine services
Constraints
Phase 2+ investment (₹20,000 crore estimate) not yet closed
Competitive response of Colombo and Jebel Ali
Triggered by this programme · horizon medium · a hypothesis, not a forecast or procurement signal.
Opportunity surfaceConfidence: High
Shipbuilding supplier localisation on the ₹69,725 crore policy base
Trigger
The Cabinet-approved shipbuilding package (24 September 2025) provides ₹69,725 crore — SBFAS ₹24,736 crore to March 2036, the Maritime Development Fund ₹25,000 crore and Shipbuilding Dock Support ₹19,989 crore — targeting 4.5 million GT of additional capacity, while Cochin Shipyard holds ~74 vessels on order and HSL's order book has grown ten-fold in three years. [16][62][65]
Industrial effect
Yard order books at Cochin, GRSE, HSL, GSL and L&T Kattupalli lengthen. Component and equipment suppliers — engines, deck machinery, electricals, outfitting — may locate near yards to serve the order flow. Import dependence in marine engines and advanced systems could fall if supplier parks form around the PSU yards. Benefit capture depends on SBFAS disbursement rules and yard slot availability.
Potential opportunity
Potential demand for marine component manufacturing, outfitting services and yard-adjacent supplier parks under the shipbuilding package.
Affected sectors
Shipbuilding · Marine equipment
Constraints
SBFAS guidelines and first disbursements not yet on file
Deep import dependence in engines and advanced systems persists
Triggered by this programme · horizon long · a hypothesis, not a forecast or procurement signal.
Sagarmala opportunity intelligence register
The programme-level register classifies each opportunity as documented demand, emerging opportunity, analytical hypothesis or research lead — with the trigger sourced and the reasoning labelled.
Documented demandA · Port modernisation & new portsConfidence: high
Follow-on marine works and equipment demand at Vadhavan (2026-2035)
Trigger
The ₹76,220 crore Vadhavan port is under construction: a ₹5,301 crore breakwater EPC awarded to Afcons (June 2026) and a dredging/reclamation letter of award to an ITD Cementation–DEME–Jan De Nul JV (March 2025). [69][83]
Techadyant reasoning
A 298 MTPA offshore port implies successive procurement waves beyond the first two packages: quay-wall and landside civil works, mechanisation packages (ship-to-shore and yard cranes), utilities, and a maintenance regime for the 10.14 km breakwater and dredged channel. The first two awards document the demand; the composition of later waves is analysis.
Plausible customers
Port SPV (VPPL) · EPC majors · Dredging contractors · Crane OEMs and integrators
Dependencies & constraints
Reclamation completion and phasing · VPPL procurement calendar · Cabinet-approved cost schedule holding · Award value concentration in large international EPCs may limit Indian supplier share · Marine works require classification and track record that mid-size Indian firms may lack
Reviewed 10 Oct 2026 · a hypothesis register, not a forecast or procurement signal.
Documented demandA · Port modernisation & new portsConfidence: high
Port mechanisation and crane demand — and a localisation gap
Trigger
ZPMC shipped 24 RMG cranes plus quay cranes for Vizhinjam (third batch January 2024); Konecranes booked an order for 30 E-Hybrid RTGs from an Indian greenfield container terminal in Q3 2025 (delivery Q1 2027); Vizhinjam Phase 1 crossed 1 million TEUs in its first year. [70][71][50]
Techadyant reasoning
Container-terminal equipment demand is running at multi-terminal scale (Vizhinjam expansion phases, Kamarajar's second container terminal tender, Mundra programmes). Crane supply is foreign-led today — ZPMC for STS/RMG, Konecranes for RTG. Every new deepwater berth widens the equipment pipeline and the case for local assembly, spares and service capability. The 'make-in-India crane' angle is analysis, not an announced policy.
Plausible customers
Terminal operators · Port authorities · Crane OEMs' Indian subsidiaries
Dependencies & constraints
Terminal construction pipeline (Vadhavan, Vizhinjam later phases, Kamarajar CT2) · Equipment financing cost · No Indian STS-crane OEM of scale exists today; localisation would need a policy push · Konecranes order does not name its terminal — treated as a demand signal only
Evidence still needed
Terminal-wise equipment tender pipelines; any duti/export-promotion measures on port equipment.
Reviewed 10 Oct 2026 · a hypothesis register, not a forecast or procurement signal.
Documented demandE · Coastal shipping & IWTConfidence: high
Shipbuilding supplier localisation under the ₹69,725 crore package
Trigger
The Cabinet-approved shipbuilding package (24 September 2025) provides ₹69,725 crore: SBFAS ₹24,736 crore to March 2036, the Maritime Development Fund ₹25,000 crore and Shipbuilding Dock Support ₹19,989 crore, targeting 4.5 million GT of capacity. Cochin Shipyard holds a ₹2,000 crore LNG-feeder order with ~74 vessels on order; HSL's order book grew from ~₹2,000 crore to ₹20,000+ crore in three years; L&T delivered INS Samarthak (September 2026). [16][62][65][67]
Techadyant reasoning
Subsidised hull demand with a credit-note mechanism is designed to pull component and equipment suppliers into the yards: marine engines, deck machinery, electrical systems, piping, outfitting and steel fabrication. The order books documented at the PSU yards give the demand base; the supplier-shift is the intended mechanism of the policy and an analytical inference about who benefits.
Plausible customers
Shipyards (hull demand) · Marine equipment and component makers · Steel and outfitting suppliers · Marine electrical system suppliers
Dependencies & constraints
SBFAS disbursement rules and uptake · Yard slot availability · Classification and navy-civil order mix · Deep import dependence in engines and advanced systems persists · Credit-note benefit for shipbreaking does not itself create component supply
Evidence still needed
SBFAS guidelines text; first subsidy disbursements; supplier-park announcements near yards.
Reviewed 10 Oct 2026 · a hypothesis register, not a forecast or procurement signal.
Documented demandB · Port connectivityConfidence: medium
Port-connectivity EPC pipeline from 144 planning-stage projects
Trigger
The Comprehensive Port Connectivity Plan identifies 294 rail/road projects: 84 completed, 66 under implementation and 144 (42 rail, 102 road) under planning; Odisha's doubling of Haridaspur–Paradip alone is ₹2,542 crore. [8][11]
Techadyant reasoning
144 planning-stage projects are a forward pipeline of rail and road EPC packages concentrated in port-hinterland corridors. The executed examples (Obulavaripalle–Krishnapatnam, Haridaspur–Paradip) document both the delivery model (SPV + SDCL equity) and the scale. Contractors, rail-siding fabricators and signalling suppliers are the plausible capture points; the timing of tenders is not on file.
Plausible customers
Rail and road EPC contractors · SPV partners (SDCL/SMFCL equity) · Siding and signalling suppliers
Dependencies & constraints
Railways/MoRTH budget priority for port links · GatiShakti network-planning clearances · Planning-stage projects may be descoped or delayed · Land acquisition remains the binding constraint on rail approaches
Evidence still needed
Project-wise DPR status for the 144 planning-stage links.
Reviewed 10 Oct 2026 · a hypothesis register, not a forecast or procurement signal.
Emerging opportunityA · Port modernisation & new portsConfidence: medium
Transshipment ecosystem services around Vizhinjam
Trigger
Vizhinjam Phase 1 (1 M TEU design) commenced commercial operations on 3 December 2024 and crossed 1 million TEUs in its first year; later phases target ~5.7 M TEU capacity; the port is designed to capture ~50% of India's container transshipment currently handled at Dubai, Colombo and Singapore. [4][82]
Techadyant reasoning
A transshipment hub changes the local service economy: feeder operators re-slot Indian coastal calls, CFS/ICD operators rebalance gate volumes, and marine services (bunkering, fresh water, crew changes, repairs) scale with vessel calls. Kerala's service-sector base could capture share of these flows. None of this is contracted yet; it is reasoned from the documented traffic outcome.
Plausible customers
Feeder and coastal shipping operators · CFS/ICD and trucking firms · Marine service providers · Ship chandlers and bunkering suppliers
Dependencies & constraints
Phase 2+ investment decisions (₹20,000 crore estimate) · Mainline network commitment depth · Competitive response of Colombo and Jebel Ali · Transshipment cargo is contestable — loyalty is not guaranteed · Service ecosystem depth (bunkering, repairs) currently thin relative to Colombo
Evidence still needed
Phase 2 financial closure; mainline call frequency data; marine-services investment announcements in Kerala.
Reviewed 10 Oct 2026 · a hypothesis register, not a forecast or procurement signal.
Emerging opportunityE · Coastal shipping & IWTConfidence: medium
Coastal and Ro-Pax vessel demand from modal-share policy
Trigger
29 Ro-Pax projects worth ₹1,233 crore taken up (Ghogha–Hazira operational with ~36,000 trucks moved); seven coastal berths completed adding 9.84 MTPA; the Coastal Cargo Promotion Scheme targets raising coastal shipping's modal share from 6% to 12% by 2047; coastal cargo at major ports rose to 213.45 MT in FY26. [4][35][26]
Techadyant reasoning
Doubling modal share implies a fleet: Ro-Pax vessels, coastal bulkers and feeders, plus terminal-side equipment and service networks. Ghogha–Hazira's truck volumes document the traffic-formation effect; the fleet build-out is the analytical consequence. Indian yards (CSL's feeder orders) are the natural suppliers, connecting this surface to the shipbuilding package.
Plausible customers
Shipping lines and coastal operators · Shipyards · Terminal operators at coastal berths · Marine insurers and classifiers
Dependencies & constraints
CCPS operational details beyond the budget announcement · Vessel financing availability (SMFCL role) · Port-side coastal berth rollout · CCPS is an announcement — guidelines and outlay not yet captured · Coastal economics remain sensitive to fuel and GST treatment
Evidence still needed
CCPS scheme guidelines and outlay; SMFCL coastal-vessel lending pipeline.
Reviewed 10 Oct 2026 · a hypothesis register, not a forecast or procurement signal.
Emerging opportunityD · Coastal community developmentConfidence: medium
Cold-chain and processing capacity on completed fishing-harbour infrastructure
Trigger
Eleven fishing-harbour projects costing ₹1,057 crore are completed, benefiting 30,000+ fishermen (ministry statement); additional harbours are under implementation (Visakhapatnam ₹178.51 crore; Chennai; Kulai). [4]
Techadyant reasoning
Landing infrastructure creates the precondition, not the cold chain itself: ice plants, cold storage, freezing and processing capacity near harbours is the private investment gap that public landing-centre modernisation could unlock. Kerala and Karnataka harbour clusters are natural first locations. The linkage from harbour completion to cold-chain investment is analytical; no anchor cold-chain investor at a Sagarmala harbour is on file.
Plausible customers
Cold-chain operators · Seafood processors and exporters · Ice-plant and refrigeration equipment suppliers
Dependencies & constraints
Harbour operations and maintenance quality · Power reliability at landing centres · Export-demand cycles for seafood · Beneficiary counts are programme-reported, not audited outcomes · Cold-chain economics depend on export prices, not infrastructure alone
Evidence still needed
Private cold-storage investments announced near Sagarmala harbours; harbour utilisation data.
Reviewed 10 Oct 2026 · a hypothesis register, not a forecast or procurement signal.
CEZ land and industrial-development services — if notification happens
Trigger
14 CEZs were identified with perspective plans prepared for all; CEU priority locations proposed at Kandla, Paradip, Ennore and Vizag; but no project has been sanctioned for financial assistance under the port-led industrialisation pillar (August 2026). [48][23][9]
Techadyant reasoning
If even a few CEZs move to notified land with utilities, the immediate demand is for industrial-development services: master planning, land development, utilities EPC, and then anchor-plant construction in petrochemicals, food processing and electronics. The ports already handling those commodity chains (Dahej, Paradip, Krishnapatnam) are the likely first movers. This is a conditional hypothesis — the trigger evidence documents the absence, not the beginning.
Plausible customers
State industrial development corporations · Industrial-land developers · Anchor manufacturers in import-heavy sectors · Utilities EPC firms
Dependencies & constraints
Cabinet/State notification of at least one CEZ · Land assembly and environmental clearance · Anchor-investor commitments · Ten years after identification the pillar remains unfunded at scheme level · CEZ geography overlaps existing PCPIR/SIR frameworks (e.g. Dahej PCPIR, Dholera SIR) which already deliver industrial land
Evidence still needed
Any CEZ notification in the Gazette; state CEZ legislation; anchor MoUs tied to CEZ land.
Reviewed 10 Oct 2026 · a hypothesis register, not a forecast or procurement signal.
Research leadE · Coastal shipping & IWTConfidence: low
IWT terminal operations and NW-5 mineral freight
Trigger
NW-1 carries ~16.38 MT with 3 MMTs and 1 intermodal terminal completed; NW-5 Phase-1 (Talcher–Dhamra–Paradip) is under implementation and named first among 20 new waterways in Budget 2026-27; national-waterway cargo is claimed at 218 MMT for FY26 (flagged — see discrepancies). [31][11][35]
Techadyant reasoning
NW-5 would give Odisha's coal and mineral belt a water alternative to congested rail; if the 218 MMT FY26 claim is real, a large unexplained share sits outside NW-1/2/3 and needs identification (possibly coastal shipping reclassification or other NWs). Both the operator economics on NW-5 and the composition of the 218 MMT claim are open questions requiring research before this surface can be graded above research lead.
Reviewed 10 Oct 2026 · a hypothesis register, not a forecast or procurement signal.
Research leadA · Port modernisation & new portsConfidence: low
Port digitisation and data systems (NNSTC/ONOP direction)
Trigger
Sagar Aankalan benchmarking now covers 47 terminals; JNPA is ranked 22nd in the World Bank CPPI; the July 2026 reply references National Nodal Strategy for Transshipment at Ports / One Nation One Port Process without captured dates or costs; 26 port data layers are mapped on GatiShakti. [32][13][12]
Techadyant reasoning
Performance-index pressure and process-standardisation programmes tend to pull port-community-system software, terminal operating systems and data-integration work. India's TOS base is largely foreign (Zodiac, Navis-class). The direction is real but the procurement specifics are not yet captured — hence a research lead, not an emerging opportunity.
Plausible customers
Port authorities · Terminal operators · Port IT integrators · Data-platform vendors
Dependencies & constraints
NNSTC/ONOP formal notification and funding · Port-level IT budgets · No captured budget or scheme text for NNSTC/ONOP · Procurement cycles at ports are long
Evidence still needed
NNSTC/ONOP scheme documents; port IT tender pipelines.
Reviewed 10 Oct 2026 · a hypothesis register, not a forecast or procurement signal.
Programme scorecard (industrial connectivity, supply-chain impact, strategic importance, opportunity potential): not published. Techadyant shows a score only once its methodology is documented and the inputs exist — see the node-level methodology.
16 · Related projectsFact
Projects linked to the programme
Projects in the Atlas that carry a sourced link to this programme. New linked projects appear here automatically.
Project
Link
Status
Cost
Contractors
Industrial node
Road over bridge at LC-235, Deendayal Port (Kandla)Port-connectivity road over bridge at a rail level crossing · Gujarat
approvedApproved by MoPSW after appraisal by its Delegated Investment Board (reported 4 Apr 2026).
₹132.51 cr
Not documented
None directly
Vadhavan Port development (greenfield major port, artificial island)Greenfield deep-draft major port on an artificial island off Vadhavan (Palghar, Maharashtra) · Maharashtra
under constructionBreakwater EPC (₹5,301 crore, Afcons) awarded June 2026; dredging and reclamation to an ITD Cementation–DEME–Jan De Nul JV (LoA March 2025).
₹76,220 cr
Not documented
None directly
Vizhinjam International Seaport, Phase 1 (deepwater transshipment port)Deepwater container transshipment port, Phase 1 (1 M TEU design) · Kerala
operationalCommercial operations since 3 December 2024; dedicated by the Prime Minister on 2 May 2025; crossed 1 million TEUs in its first year.
₹8,867 cr
Not documented
None directly
Contractors are listed only where a source names them on this project — never inferred from sector or geography. “Not documented” means no source on file yet, not that none exists.
Sagarmala feeds traffic toMajor ports cargo throughputLogistics reference layerMajor-port throughput is the outcome measure Sagarmala reports. [4]
19 · Related signals
Latest Sagarmala signals
Surfaced automatically when a Signal names the programme, is linked to it by Techadyant, or covers a node or project it reaches. The reason is shown on each card.
Linde India has secured a land parcel in Sanand, Gujarat, for a semiconductor packaging-gas facility - its second India chip-gas site after the Dholera plant set to supply Tata''s fab. Electronic specialty gases are a real, under-noticed chip dependency; the supply is being localised, but largely by global majors - which brings the molecule onshore without yet localising the technology or the ownership.
Why it is here: On Sanand, a node this programme reaches
The foundation stone has been laid for India''s first port-based e-methanol plant at Deendayal Port (Kandla) - a Rs 2,300 crore, 150 TPD joint venture between the port authority and Assam Petro-Chemicals, using renewable power, water and biogenic CO2 to make green marine fuel for the Asia-Europe corridor. Maritime fuel is a hard dependency layer for trade and defence logistics; siting green-fuel production at the port where ships already stop is a real move, but a foundation stone is not operating capacity.
Why it is here: A port-based industrial plant at Deendayal (Kandla) — an instance of the port-led industrialisation Sagarmala targets; not documented as a Sagarmala project.
MeitY Secretary S Krishnan announced on 18 August that three semiconductor facilities — Micron, Kaynes and CG Semi, all at Sanand in Gujarat — have entered commercial production under ISM 1.0, with five to six projects expected to be live by end-2026. The Union Cabinet has approved ISM 2.0 with an outlay of Rs 1,27,500 crore, and PM Modi will inaugurate SEMICON India 2026 on 17 September.
Why it is here: On Sanand, a node this programme reaches
Deendayal Port road over bridge (₹132.51 crore) approved under Sagarmala [6]
Major ports handle a record 915.17 MT in FY 2025-26; Sagarmala 2.0 proposed [4]
Value lags count Derived
Completed projects are 37% of the portfolio by count but about 26% by value (24 Mar 2026). [4]
CEZs are still plans Fact
The 14 Coastal Economic Zones remain proposals with perspective plans; in August 2026 Parliament was told that no project has been sanctioned for financial assistance under the port-led industrialisation pillar of the Sagarmala scheme. [9][5]
Pillar-wise portfolio values Fact
The 839-project pillar-wise value split (Mar 2025) is held via a secondary mirror of the ministry page; the primary table could not be captured because sagarmala.gov.in blocks automated access. [75]
Data gaps
What this page does not yet know
The full 845-project portfolio is not itemised here; the ministry does not publish a machine-readable list and sagarmala.gov.in blocks automated capture. Portfolio statistics and pillar splits are held with dates and scopes.
Terminal-level inventories for all major ports are not yet captured; port-level and terminal-level throughput are kept separate to prevent double counting.
Anchor-unit status for the 14 CEZs is a verified absence (no sanction), not missing data.
Kamarajar Port's proposed second container terminal has no URL-bearing source on file and is excluded from the project database.
Employment figures (~1 crore jobs projected) are ministry projections, not measured outcomes.
The scheme-funding lifecycle (186 sanctioned, 58 withdrawn, 128 funded) rests solely on the Lok Sabha AU2431 annexure of 13 Feb 2026. The PDF could not be independently re-retrieved on 2026-10-11 (sansad.in returned no content), and secondary coverage corroborates only the 78-completed figure. Treat the sanction and withdrawal counts as single-source pending re-capture.
CoverageDerived from the graph
What this database does and does not hold
Record counts are enforced against the data files by the build validator — the manifest cannot drift from the records. Verified facts, official reported values, inferred relationships and unverified research leads are kept separate throughout.
Tier A · Programme foundationcomplete
Programme dossier with approval, NPP, objectives, pillars, institutions, funding, statistics, Sagarmala 2.0 status, vision links and dated timeline (dossier.json)
Policy and programme evolution records (policies.json)
Source registry: 78 new Tier-1/Tier-2/Tier-3 sources merged into the shared registry
Tier B · National maritime infrastructuredefensible core
All 12 operational major ports plus Vadhavan and Galathea Bay (under construction) with coordinates, authorities, FY25/FY26 throughput (ports.json)
12 of the largest non-major ports registered out of 217 notified — deliberately selective
Portfolio statistics time series (802 → 839 → 845 projects) and scheme-funded lifecycle (pillar-projects.json)
Cargo time series FY2014-15 to FY2025-26 for major, non-major and all ports; container, capacity, TRT, PBD, IWT and coastal series (port-performance.json)
Flagship project cards for 13 documented projects across all five pillars
Not covered: Full itemisation of the 845-project portfolio (not published in machine-readable form) · Terminal-by-terminal inventories for all major ports · The remaining ~205 non-major ports
Tier C · Industrial & commercial depthseeded
All 14 CEZs with linkage ports, intended sectors and verified 'proposed' status (industrialisation.json)
24 companies with 40+ evidenced relationships across port operation, terminals, shipping, shipbuilding, dredging, EPC and equipment (companies.json)
Coastal community dataset: fishing harbours, skilling, tourism, Ro-Pax outcomes (community.json)
Connectivity records: 9 documented connections plus the CPCP aggregate (connectivity.json)
Not covered: Company financials beyond cited scale facts · Anchor-unit status for CEZs (none exists — verified absence) · State maritime board project inventories
Tier D · Analytical intelligenceseeded
Ten opportunity records across all four classifications with sourced triggers and labelled reasoning (opportunities.json)
Portfolio-versus-delivery gap analysis (value lags count)
Port-to-hinterland reading through the existing Atlas relationship layer (connectivity.json atlas_node_links)
Time-series trends with definitional caveats (port-performance.json)
Discrepancy register
Sagarmala portfolio totals: 839 projects / ₹5.79 lakh crore (27 Mar 2025 PIB backgrounder) vs 845 projects / ₹6.06 lakh crore (24 Mar 2026 PIB backgrounder). PIB's own August 2026 social posts still cite the older 839 figure. Resolution: Both retained with dates; the 845/₹6.06 lakh crore figure (24 Mar 2026) is treated as current.
Sagarmala 2.0 budgetary support: ₹40,000 crore (March 2025 PIB-derived reports) vs ₹85,482 crore (April 2026 PIB backgrounder). Resolution: Superseded-on-file relationship recorded; both observations retained with dates.
Major-port FY 2025-26 total: 915.17 MT (final PIB release, 5 April 2026) vs 914.73 MT (TRW advance estimate). Resolution: Both retained and labelled; the final PIB figure is preferred for citation.
Vessel turnaround time: Three incompatible series: 96→49.5 hrs (2014→2025, PIB backgrounder); 94→48.8 hrs (2014→2025-26, PIB factsheet); 52.87→48.84 hrs (FY21-22→FY25-26, RS reply); BPS revised-definition 52.82→58.58 hrs (FY24→FY25). Resolution: Series kept separate and labelled; never combined into one trend.
IWT cargo FY 2025-26: MoPSW claims 218 MMT for FY26 versus final FY25 statistics of 145.84 MT — a 50% jump with no NW-wise FY26 publication found to cross-check. Resolution: Claim recorded with its sources and flagged; not treated as verified.
Port capacity baselines: Ministry sources quote 555 MTPA (FY13-14), 873 MMTPA (2014), 1,681 MTPA (FY24-25), 1,680.94 MTPA (BPS FY25) and 1,728 MMTPA (2026) for major ports, and ~1,400 MTPA (2013-14) → 2,818 MTPA (Mar 2026) combined. Resolution: Points retained with their own baselines; marked heterogeneous and not strictly comparable.
Known gaps
sagarmala.gov.in is WAF-blocked for automated capture — the 14-CEZ table and the 839-project pillar split are held via secondary mirrors (SCC Times quoting the 2016 PIB release; Wikipedia mirroring the ministry page). Re-fetch from a network with government access.
The PIB release for the 19 June 2024 Vadhavan Cabinet approval could not be pinned to a PRID; the fact is evidenced through BPS 2024-25, the SPV site and the 4 August 2026 Lok Sabha reply instead.
Kamarajar Port's proposed second container terminal (₹4,288 crore tender, June-August 2026 trade reports) has no URL-bearing source captured — excluded from the flagship project list.
Per-project cost mapping of all 128 scheme-funded projects is incomplete because the sansad annexure PDF's two-column text flow scrambles some name-to-cost rows; project cards only carry costs verified in clear text.
No Port Blair '13th major port' designation exists (verified absence per BPS Table 1.1); A&N has 0 major and 24 non-major ports.
SCI privatisation status (reported on hold, October 2025) and the Mumbai/Kandla container-terminal operator identities could not be verified from URL-bearing sources.
Employment outcomes (~1 crore jobs projected; 30,000 fishermen benefited) are ministry statements, not audited outcomes — recorded as reported values only.
The National Productivity Council's third-party impact evaluation of Sagarmala has not been located or captured.
Facts and headline metrics come from the SID logistics reference layer and the shared Techadyant source registry; every figure carries a date and a numbered source. The Techadyant reading — why it matters, consequences, opportunity surfaces — is labelled as analysis.
Connected projects, industrial nodes, opportunities, signals and reports are not hand-listed. They are derived at build time from evidenced links in the Atlas graph, so a new project, signal or report linked to Sagarmala appears here on the next build. We don’t replicate India’s infrastructure databases. We interpret them.