Bharatmala Pariyojana

India’s highway and economic-corridor transformation.

The Techadyant questionWhich industrial locations did the corridor network make more reachable — and which parts of the programme lagged behind?

Status
Under implementation
Time horizon
Phase-I was originally targeted for 2021-22; MoRTH now targets completion of its Bharatmala projects by 2028-29.
Footprint
National highway network — economic, inter-corridor, feeder, border and port-connectivity routes
Sectors affected
Road freight · Logistics · Manufacturing clusters on corridor routes
01 · Programme at a glanceFact

What is verifiably true today

Only figures with a source on file. Each carries its own date — programme figures are published at different times, so they are not summed or compared across dates.

Approved
24 October 2017 (Phase-I) [5]As of 8 Feb 2018
Phase-I scope
34,800 km, including ~10,000 km of residual NHDP [6]As of 29 Apr 2024
Approved cost
₹5,35,000 crore (2017) [6]As of 29 Apr 2024
Awarded
26,425 km [11][7]As of 22 Jul 2026
Constructed
22,709 km (up to May 2026) [11][7]As of 22 Jul 2026
New sanctions
Discontinued since November 2023 [7]As of 22 Jul 2026
Expenditure
Rs 5,63,779 crore [11]As of 30 Jun 2026
Completion target
2028-29 (MoRTH, Jul 2026; a Mar-2026 PRS budget analysis carries 2027-28) [11]As of 22 Jul 2026
Lead ministry
Ministry of Road Transport & Highways (NHAI, NHIDCL)
Launch
Phase-I approved by the CCEA on 24 Oct 2017 [5]
SID reference record:Single-source· Planned: 34,800 km· Awarded: 26,425 km· Constructed: 19,826 km· as on 28 Feb 2025Source record →

Announced → approved → under implementation → completed → operational

  1. Announced
    —
  2. Approved
    Approved scope34,800 km · ₹5.35 lakh crore24 Oct 2017 [6]
    Cost of awarded length₹8,46,588 crore for 26,316 km — 158% of the 2017 estimate; MoRTH’s revised estimate ₹10.95 lakh crore31 Mar 2023 [6]
  3. Under implementation
    Awarded26,316 km (Mar 2023) → 26,425 km (Feb 2025 onwards)22 Jul 2026 [6][8][11][7]
    Constructed (Mar 2026)22,590 km constructed of 26,425 km awarded31 Mar 2026 [12]
    ExpenditureRs 4,92,562 crore (Feb 2025) → Rs 5,63,779 crore (Jun 2026)30 Jun 2026 [8][11]
    Completion targetProjects targeted for completion by 2028-2922 Jul 2026 [11]
  4. Completed
    Constructed13,499 km (Mar 2023) → 19,826 km (Feb 2025) → 22,709 km (May 2026)31 May 2026 [6][8][7]
    Greenfield high-speed corridors6,669 km awarded · 4,610 km completed28 Feb 2025 [8]
  5. Operational
    —
02 · Why it mattersTechadyant analysis

How Bharatmala is changing India’s industrial system

Interpretation, labelled. Sourced statements are marked Fact.

Analysis Bharatmala matters less for the kilometres it adds than for how it chose them: by corridor, along origin–destination freight routes. Corridors change which industrial locations are cheap to reach, and so where new capacity is likely to go.

Fact In practice it became an expressway programme. By March 2023, greenfield expressways were 302.75% awarded and 119.75% completed against their approved length, while coastal and port connectivity roads were 20.75% awarded and 5.2% completed. [6]

Fact The node-level effect is visible at Dholera: the 109 km NE-8 expressway, built under Bharatmala, cut Ahmedabad–Dholera travel from 2 h 15 min to 45 min when it opened for testing in Feb 2026. [1]

Fact Execution is now a finishing problem with a map: 22,709 of 26,425 awarded km were built by May 2026, but the remainder is uneven — Punjab (672 km under construction), Andhra Pradesh (382), Karnataka (334) and Uttar Pradesh (299) hold the largest pending stretches, and the completion target has moved to 2028-29. [11]

Analysis Where the pending kilometres sit is where freight gains stay locked: a corridor that is open in one state and stuck in the next delivers a fraction of its end-to-end economics, so state-level delivery speed has become the binding variable for industrial connectivity.

03 · Geographic footprintDerived from the graph

Where Bharatmala meets India’s industrial geography

Shows only industrial nodes and infrastructure reached through an evidenced project link, not the programme’s full national network. Techadyant does not replicate PM GatiShakti’s GIS. National footprint: national highway network — economic, inter-corridor, feeder, border and port-connectivity routes. The linked roads follow NHAI’s own Bharatmala map, and the toggles add its wider network (expressways, economic and national corridors, inter-corridor and feeder roads). That map is marked not to scale, so every line is schematic: it shows where a corridor runs, not its surveyed alignment.

DholeraSriperumbudur–Oragadam
Industrial node · Gujarat

Dholera

India’s only approved commercial logic fab sits in a node whose road link has arrived, whose airport is close, and whose rail link is five years out. ICS: 55 (Moderate).

SemiconductorsSemiconductor fabricationElectronic materialsSolar
Open dossier →

Schematic. Positions are approximate centroids; distances on dossiers are straight-line and labelled as such.

04 · Programme componentsFact

How the programme is built

Expand a component for its scope and the latest sourced progress.

Economic corridors~9,000 km · ₹1,20,000 crore approvedUnder implementation

Freight-heavy origin–destination routes between economic centres.

Progress: 94.74% awarded · 42.30% completed (Mar 2023)

[5][6]
Inter-corridor & feeder roads~6,000 km · ₹80,000 crore approvedUnder implementation

Links between corridors and feeders into them.

Progress: not captured from a primary source.

[5][6]
National corridors efficiency improvement~5,000 km · ₹1,00,000 crore approvedUnder implementation

Decongesting existing national corridors (ring roads, choke points).

Progress: not captured from a primary source.

[5][6]
Border & international connectivity roads~2,000 km · ₹25,000 crore approvedUnder implementation

Roads to borders and neighbouring-country links.

Progress: 80% awarded · 62.8% completed (Mar 2023)

[5][6]
Coastal & port connectivity roads~2,000 km · ₹20,000 crore approvedUnder implementation

Road access to ports and coastal areas.

Progress: 20.75% awarded · 5.2% completed (Mar 2023)

[5][6]
Greenfield expressways~800 km · ₹40,000 crore approvedUnder implementation

Access-controlled high-speed corridors.

Progress: 302.75% awarded · 119.75% completed vs approved length (Mar 2023)

[5][6]
Residual NHDP~10,000 km · ₹1,50,000 crore approvedUnder implementation

Balance works of the earlier National Highways Development Project.

Progress: not captured from a primary source.

[5][6]
05 · Connected industrial nodesDerived from the graph

Industrial nodes affected

Each card shows the evidence path from programme to node. A node appears only when a sourced project links them; two locations being close is not enough.

  1. ProgrammeBharatmala
  2. ProjectAhmedabad–Dholera Greenfield Expressway (NE-8)
  3. Industrial nodeDholera

India’s only approved commercial logic fab sits in a node whose road link has arrived, whose airport is close, and whose rail link is five years out.

  1. ProgrammeBharatmala
  2. ProjectBengaluru–Chennai Expressway (greenfield)
  3. Industrial nodeSriperumbudur–Oragadam

India’s densest electronics-assembly belt sits within ~50 km of two major ports and an international cargo airport — the test of whether gateway proximity is already priced in.

06 · Connected logistics systemDerived from the graph

The connected logistics system

Road → rail → DFC → logistics parks → ports → air cargo → industrial nodes. Filled only from records linked to this programme (Atlas projects and the SID logistics layer). An empty row means no linked record yet, not that nothing exists.

  1. Road
    Ahmedabad–Dholera Greenfield Expressway (NE-8) trial · linked projectBengaluru–Chennai Expressway under construction · linked projectDelhi–Mumbai Expressway (Delhi–Vadodara–Mumbai Greenfield Expressway) under construction · linked projectDelhi–Mumbai Expressway JNPT spur (Package 13) under construction · linked projectDelhi–Amritsar–Katra Expressway under construction · linked projectAmritsar–Jamnagar Expressway (Economic Corridor EC-3) under construction · linked projectRaipur–Visakhapatnam Economic Corridor (NH-130CD, EC-15) under construction · linked projectDwarka Expressway (Delhi–Gurugram elevated urban expressway) operational · linked projectZojila Tunnel (NH-1 Srinagar–Leh) under construction · linked projectBharatmala Pariyojana road network (Phase-I aggregate) reference record · SID logistics layer
  2. Rail
    No linked record
  3. Dedicated freight corridor
    No linked record
  4. Logistics parks & terminals
    No linked record
  5. Ports
    No linked record
  6. Air cargo
    No linked record
  7. Industrial nodes
07 · Industrial consequencesTechadyant analysis

What Bharatmala changes for industry

Each statement is tagged Fact (sourced) or Analysis (Techadyant interpretation).

Manufacturing

Corridors reprice industrial locations

Fact NE-8 cut Ahmedabad–Dholera travel time from 2 h 15 min to 45 min (Feb 2026). [1]

Analysis For a greenfield node, the first fast road link is often what makes construction, workforce and early logistics practical before rail arrives.

Logistics

Trunk speed improved faster than the first and last mile

Fact Expressways over-delivered while MMLPs (0 of 35) and port-connectivity roads (5.2%) lagged as of Mar 2023. [6]

Analysis Freight gains on the trunk can be absorbed at port gates and consolidation points that the programme did not build.

Fact The Delhi–Mumbai Expressway — 1,386 km, ~Rs 1 lakh crore, ~80% complete (Jul 2026) — includes a dedicated ~3 km spur to Jawaharlal Nehru Port (Package 13). [12][28]

Analysis A trunk this fast shifts the bottleneck to interchanges and city gates, which is where consolidation capacity — not haulage — captures the gain.

Trade

Export gateways were the weak link

Fact Coastal & port connectivity was 20.75% awarded and 5.2% completed (Mar 2023). [6]

Analysis The port leg is now addressed partly through Sagarmala’s port-connectivity pillar, so gateway access depends on two programmes.

Fact PIB describes the Raipur–Visakhapatnam corridor (EC-15) as directly linked to Visakhapatnam Port and the Chennai–Kolkata NH, with “improved connectivity to ports and industrial hubs, quicker exports, smoother supply chains”. [13]

Analysis Interior mineral and steel belts that gain a designed port axis may find export logistics materially cheaper once the corridor opens (targeted December 2026).

Regional development

Corridor alignment follows industrial corridors

Fact The Bengaluru–Chennai Expressway, built under Bharatmala Phase-I, is described as a priority corridor of the Chennai–Bengaluru Industrial Corridor, with industrial areas and a proposed MMLP on its Karnataka section. [9]

Analysis Where highway and industrial-corridor planning coincide, the highway becomes the corridor’s spine — the pattern to watch at other NICDP nodes.

Fact The 13.153 km Zojila tunnel, listed by NHIDCL under Bharatmala works, achieved breakthrough in June 2026 — the border component’s flagship move toward an all-weather Srinagar–Leh axis (reported opening target February 2028). [17][15][18]

Supply chains

Road remains the default mode for time-sensitive inputs

Analysis Faster corridors make road more competitive against rail for components and finished goods even as the DFC opens. That may slow the modal shift the freight corridors were built for.

08 · Supply-chain implications

Where the programme sits in the supply chain

Input → manufacturing node → freight network → logistics node → port / airport → market.

  1. Input

    Components and materials move by road over economic and feeder corridors. Analysis

  2. Manufacturing node

    Industrial nodes gain fast road access — e.g. Dholera via NE-8. Fact [1]

  3. Freight network

    22,709 km of Phase-I corridors constructed (May 2026). Fact [7]

  4. Logistics node

    The 35 planned MMLPs had not been developed as of Mar 2023 — the missing consolidation layer. Fact [6]

  5. Port / airport

    Port connectivity roads were 5.2% complete (Mar 2023); the Delhi–Mumbai Expressway adds a dedicated JNPT spur (Package 13) and PIB ties EC-15 directly to Visakhapatnam Port. Fact [6][28][13]

  6. Market

    Domestic markets gain most directly; export gains depend on the port leg. Analysis

09 · Opportunity surfacesOpportunity surface

Where new opportunity may appear

Analytical hypotheses with a sourced trigger, stated constraints and a confidence label (High / Medium / Emerging). Not forecasts, and not procurement signals.

Opportunity surfaceConfidence: Medium

Road-bridged materials and gas logistics for the Dholera fab before rail arrives (2026–2031)

Trigger
The NE-8 expressway is open for testing while the Sarkhej–Dholera rail line is approved only for completion by 2030-31; Fujifilm has signed an MoU for a phased materials plant inside the SIR. [1][2][4]
Industrial effect
For roughly five years every bulk chemical, gas cylinder and tool spare reaches the fab by road, over ~160–260 km (straight-line) from Gujarat’s ports. Fab ramp-up depends on dependable, contamination-controlled road logistics for hazardous and high-purity inputs. Materials makers (Fujifilm MoU) and gas suppliers locating inside the SIR shorten the most fragile inbound legs. Import dependence on photoresists, slurries and high-purity chemicals persists, but the physical exposure moves from long road hauls to on-site supply.
Potential opportunity
Potential demand for hazmat-certified, high-purity chemical and gas logistics, on-site storage and cylinder/ISO-tank management serving the fab and its vendor park during the pre-rail window.
Affected sectors
Electronic materials · Specialty gases
Constraints
  • Fab production timeline could slip, delaying demand.
  • Tata and global gas/chemical majors may run captive logistics, leaving little room for third parties.
  • Vendor-park and materials MoUs may not convert to builds.

Via Ahmedabad–Dholera Greenfield Expressway (NE-8) · horizon near · a hypothesis, not a forecast or procurement signal.

Opportunity surfaceConfidence: Emerging

Fab-grade air-cargo handling at Dholera’s new airport

Trigger
Dholera International Airport is under construction next to the SIR, with a planned 2,500 sq m cargo hub and a direct expressway interchange. [3][1]
Industrial effect
Time-critical shipments could shift from Ahmedabad (~105 km straight-line) to an on-site airport. Wafer, spare-part and specialty-material movements would be faster and handled closer to the cleanroom. A small general-purpose cargo hub may not meet semiconductor needs (ESD, vibration, temperature, bonded clearance).
Potential opportunity
Potential opening for semiconductor-specialised air-cargo handling, bonded storage and customs-brokerage capability sized to the fab rather than to general cargo.
Affected sectors
—
Constraints
  • Airport opening date and cargo-terminal scope are single-source and unconfirmed.
  • Air-freight volumes depend on fab ramp; Ahmedabad may remain the default gateway.

Via Ahmedabad–Dholera Greenfield Expressway (NE-8) · horizon medium · a hypothesis, not a forecast or procurement signal.

Opportunity surfaceConfidence: Emerging

Port-access roads and logistics parks — the parts of Bharatmala Phase-I that lagged

Trigger
Parliament’s Public Accounts Committee (Apr 2024, on CAG audit data to Mar 2023) found coastal & port connectivity roads only 5.2% completed and none of 35 planned multimodal logistics parks developed, while the highway corridors raced ahead. New Phase-I sanctions have been discontinued since Nov 2023. [6][7]
Industrial effect
Freight gains on the trunk can be absorbed at the port gate and the first/last mile. Export-oriented clusters near ports may see trunk-route gains without matching gateway gains.
Potential opportunity
Port-access, consolidation and logistics-park capacity — public or private — could fill the gap the programme left, under whichever successor framework funds it.
Affected sectors
Logistics · Port-linked manufacturing
Constraints
  • The PAC findings are dated March 2023; some MMLPs and port links may have progressed since — current status is not captured here.
  • Successor funding framework for new highway sanctions is not documented in this layer.
  • Port-connectivity works are also funded under Sagarmala, so the gap may be filled there.

Triggered by this programme · horizon medium · a hypothesis, not a forecast or procurement signal.

Opportunity surfaceConfidence: Medium

Warehousing and distribution consolidation along the Delhi–Mumbai Expressway

Trigger
The 1,386 km, ~Rs 1 lakh crore Delhi–Mumbai Expressway is ~80% complete (Jul 2026) with full completion signalled within two years, and delivers a dedicated ~3 km spur to Jawaharlal Nehru Port (Package 13). [29][28]
Industrial effect
Interchange locations along Rajasthan, Madhya Pradesh and Gujarat become the natural points where North–South freight consolidates or breaks bulk, cutting drayage into the trunk. Distribution-intensive industries (consumer goods, electronics, auto components) could re-site regional warehouses from city edges to expressway interchanges.
Potential opportunity
Warehouse parks, 3PL consolidation hubs and truck-support services at DME interchanges — private or PPP — could capture the modal shift; the operator ecosystem (e.g. national logistics-park developers) is already positioned along the axis.
Affected sectors
Logistics · Warehousing · Third-party distribution
Constraints
  • Multimodal Logistics Parks planned under the programme were not developed as of Mar 2023, so the public consolidation layer is missing — private facilities would fill that role.
  • Land assembly and state-level warehousing policy along the alignment vary.
  • Toll pricing and the pace of the final Gujarat/Maharashtra sections affect the traffic ramp.

Triggered by this programme · horizon medium · a hypothesis, not a forecast or procurement signal.

Opportunity surfaceConfidence: Medium

Mineral-belt export logistics via the Raipur–Visakhapatnam corridor

Trigger
The 465 km, Rs 16,482 crore Raipur–Visakhapatnam Economic Corridor (NH-130CD) is expected to complete by December 2026 and, per PIB, will be "directly linked to the Visakhapatnam Port and the Chennai-Kolkata National Highway" with "improved connectivity to ports and industrial hubs, quicker exports, smoother supply chains". [13]
Industrial effect
Mine, plant and industrial-hub traffic in the belt gains a designed port axis for the first time, replacing mixed-traffic state-road routings. Steel, cement, aluminium and mineral exporters in the belt may find port-gate logistics materially cheaper and more predictable, strengthening the case for downstream processing at interior plants.
Potential opportunity
Freight forwarding, rakes-to-road transloading, port-yard capacity and industrial last-mile services along the corridor could grow with the export flow once the corridor opens.
Affected sectors
Mining & metals · Port logistics · Steel
Constraints
  • Completion date (Dec 2026) is a target from a Dec 2025 release; slippage is possible.
  • Freight volumes are not published here — no market size is implied.
  • Rail (DFC feeder and IR lines) competes for the same mineral flows.

Triggered by this programme · horizon near · a hypothesis, not a forecast or procurement signal.

Opportunity surfaceConfidence: Emerging

All-weather Ladakh logistics once the Zojila tunnel opens

Trigger
The 13.153 km Zojila tunnel — listed by NHIDCL under Bharatmala Pariyojana works — achieved final breakthrough on 9 Jun 2026; opening is reported to be targeted around February 2028. [15][17][18]
Industrial effect
Srinagar–Leh road access becomes year-round, ending the winter window in which the region is effectively road-isolated. Supply chains serving Ladakh — provisions, construction materials, tourism services — could shift from stockpiling to scheduled replenishment; tourism season may lengthen.
Potential opportunity
Scheduled trucking services, winter-grade warehousing and tourism logistics on the axis could emerge once the tunnel opens.
Affected sectors
Border logistics · Tourism · Regional supply
Constraints
  • Opening target (Feb 2028) is a press-reported estimate; finishing works at altitude have slipped before.
  • This layer records publicly documented infrastructure only; no operational or defence logistics detail is included.
  • Air cargo (Leh) will keep carrying the highest-value flows.

Triggered by this programme · horizon long · a hypothesis, not a forecast or procurement signal.

Programme scorecard (industrial connectivity, supply-chain impact, strategic importance, opportunity potential): not published. Techadyant shows a score only once its methodology is documented and the inputs exist — see the node-level methodology.

10 · Related projectsFact

Projects linked to the programme

Projects in the Atlas that carry a sourced link to this programme. New linked projects appear here automatically.

ProjectLinkStatusCostContractorsIndustrial node
Ahmedabad–Dholera Greenfield Expressway (NE-8)Greenfield access-controlled expressway · Gujaratbuilt under [1]trialOpened to the public for testing; final operational readiness being assessed (27 Feb 2026).₹5,800 crNot documenteddholera
Bengaluru–Chennai Expressway (greenfield)Greenfield access-controlled expressway · Karnataka, Andhra Pradesh, Tamil Nadubuilt under [9]under constructionDescribed as being developed under Bharatmala Pariyojana Phase-I (Jun 2026); construction progress and opening date not stated. Alignment begins at Hoskote (Karnataka) and ends at Sriperumbudur (Tamil Nadu), with last-mile to Chennai via two elevated connectors.₹17,900 crNot documentedsriperumbudur-oragadam
Delhi–Mumbai Expressway (Delhi–Vadodara–Mumbai Greenfield Expressway)Greenfield access-controlled expressway (8-lane, expandable to 12) · Delhi, Haryana, Rajasthan, Madhya Pradesh, Gujarat, Maharashtrabuilt under [12]under construction~80% complete per the Road Transport Minister (Jul 2026), with full completion signalled within two years. Sections opened progressively since Feb 2023.₹1.00 lakh crG R Infraprojects Ltd — EPC/HAM contractor (8 packages (~290 km); corridor package total disputed — 52 per undated trade press vs 53–54 in parliamentary replies) [27]H G Infra Engineering — EPC contractor (package award holder) [27]None directly
Delhi–Amritsar–Katra ExpresswayGreenfield access-controlled expressway · Punjab, Haryana, Jammu & Kashmirbuilt under [25]under constructionFirst 157.92 km (Packages 1–5, ~Rs 9,680 crore) dedicated to the nation on 17 Jul 2026; balance under construction.₹38,905 crNot documentedNone directly
Amritsar–Jamnagar Expressway (Economic Corridor EC-3)Greenfield six-lane access-controlled economic corridor · Punjab, Haryana, Rajasthan, Gujaratbuilt under [14][21]under constructionRajasthan section (>500 km) dedicated 8 Jul 2023; a further 27.1 km Deogarh–Gujarat border stretch opened Sep 2026; remaining sections under construction.—Not documentedNone directly
Raipur–Visakhapatnam Economic Corridor (NH-130CD, EC-15)Greenfield six-lane access-controlled economic corridor · Chhattisgarh, Odisha, Andhra Pradeshbuilt under [14][13]under constructionExpected completion December 2026 (PIB, Dec 2025).₹16,482 crNot documentedNone directly
Dwarka Expressway (Delhi–Gurugram elevated urban expressway)India’s first grade-separated (elevated) urban expressway · Delhi, Haryanabuilt under [19]operationalHaryana section (19 km) inaugurated 11 Mar 2024 (PIB).₹8,662 crNot documentedNone directly
Zojila Tunnel (NH-1 Srinagar–Leh)High-altitude bi-directional road tunnel (13.153 km) · Jammu & Kashmir, Ladakhbuilt under [15]under constructionFinal breakthrough achieved 9 Jun 2026; opening targeted around February 2028 (reported).₹6,809.69 crMegha Engineering & Infrastructures Ltd (MEIL) — design & construction contractor (Zojila tunnel civil works) [18][17]None directly

Contractors are listed only where a source names them on this project — never inferred from sector or geography. “Not documented” means no source on file yet, not that none exists.

11 · Geographic coverageFact

State-wise coverage matrix

Reproduced from a single dated primary source at one reporting date. Columns are the programme’s own published categories — they are state programme totals, not attributable to a single scheme, and are not summed with figures from other dates. Rows are as published, including any cross-footing artefacts.

State / UTTotal (km)Awarded (km)Constructed (km)Under construction (km)
Andhra Pradesh2,5251,9361,554382
Assam43343141417
Bihar1,5721,159815344
Chhattisgarh57147142249
Delhi2032031958
Goa2626260
Gujarat1,5771,1941,068126
Haryana1,0581,0581,01147
Himachal Pradesh16716711750
Jammu & Kashmir43325117972
Jharkhand1,000801557244
Karnataka2,0591,6031,269334
Kerala1,126708584124
Madhya Pradesh3,0632,0171,826191
Maharashtra3,0292,1742,000174
Manipur63563557065
Meghalaya17017015317
Mizoram59359354251
Nagaland20820816840
Odisha1,58696794819
Punjab1,7641,553881672
Rajasthan2,5032,3602,26496
Tamil Nadu2,4141,4761,357119
Telangana1,7191,02695571
Tripura94946925
Uttar Pradesh3,1262,4952,196299
Uttarakhand27326420460
West Bengal87438536421
Total34,80026,42522,7093,716

State-wise Bharatmala Pariyojana lengths from the Rajya Sabha annexure (22 Jul 2026). Columns are state totals for the whole programme — lengths under different national-highway schemes are not separable at this resolution. Transcription note: state figures are reproduced exactly as published and do not cross-foot perfectly to the declared national totals (states sum to 34,801 total / 22,708 constructed / 3,717 under construction against the declared 34,800 / 22,709 / 3,716) — a rounding artefact in the annexure itself; the awarded column cross-foots exactly. [11]

Reporting date: 31 May 2026 · Download the state coverage matrix (CSV)

12 · Related companiesDerived from the graph

Companies at connected nodes

Location context only. No company listed here is claimed to hold a contract, grant or role under the programme.

14 · Related signals

Latest Bharatmala signals

Surfaced automatically when a Signal names the programme, is linked to it by Techadyant, or covers a node or project it reaches. The reason is shown on each card.

S-130 · 29 Sep 2026

Linde Secures Sanand Land for Chip Gases - Localising the Molecule, Not Yet the Ownership

Linde India has secured a land parcel in Sanand, Gujarat, for a semiconductor packaging-gas facility - its second India chip-gas site after the Dholera plant set to supply Tata''s fab. Electronic specialty gases are a real, under-noticed chip dependency; the supply is being localised, but largely by global majors - which brings the molecule onshore without yet localising the technology or the ownership.

Why it is here: On Dholera, a node this programme reaches
Read Signal →
S-113 · 18 Sep 2026

Tata's Dholera Vendor Park and Materials MoUs Begin to Populate the Supplier Layer Around the Fab

At SEMICON India 2026, Tata Electronics signed MoUs to build a 363-acre vendor park around its Dholera fab (with Ascendas First Space) and to localise critical inputs - Fujifilm's roughly Rs 800 crore materials plant, JSR's photoresists and chemicals, plus Nexperia, BESI and SCL. It is the first concrete attempt to populate the supplier layer that has to sit around India's largest silicon project.

Why it is here: On Dholera, a node this programme reaches
Read Signal →
S-012 · 30 June 2026

The Dholera Water Signal

Dholera's industrial ambition rests on a single water artery. The fab can be financed and built on schedule; the water to run it at full utilisation has to arrive every day through the Narmada canal — and that concentration, not land or capital, is the binding constraint.

Why it is here: On Dholera, a node this programme reaches
Read Signal →
S-010 · 26 Jun 2026

The vendor economy behind semiconductor fabs

Of a ₹91,000 crore mature-node fab, roughly two-thirds flows to ASML, AMAT, Lam, TEL and KLA. The Indian-capture economy lives in the remaining one-third — construction, gases, UPW, logistics and the durable industrial capabilities those build.

Why it is here: On Dholera, a node this programme reaches
Read Signal →
15 · Related research

Reports and briefings

16 · Delivery recordFact

Timeline, gaps and delays

  1. CCEA approves Phase-I (34,800 km) [5]
  2. Original completion target for Phase-I [6]
  3. Audit snapshot: 26,316 km awarded, 13,499 km completed; no MMLP developed [6]
  4. New sanctions under Phase-I discontinued [7]
  5. Public Accounts Committee reports on the CAG audit [6]
  6. 19,826 km constructed; ₹4,92,562 crore spent [8]
  7. NE-8 Ahmedabad–Dholera expressway opens for testing [1]
  8. 22,590 km constructed of 26,425 km awarded (PIB checkpoint) [12]
  9. 22,709 km constructed [7]
  10. Zojila tunnel (border component, NHIDCL) achieves final breakthrough [17][15]
  11. Bengaluru–Chennai Expressway (Karnataka, ~71 km) presented as a CBIC priority corridor [9]
  12. Cumulative expenditure reaches Rs 5,63,779 crore [11]
  13. First 157.92 km of the Delhi–Amritsar–Katra Expressway dedicated (Packages 1–5, ~Rs 9,680 crore) [23]
  14. Rajya Sabha reply: completion targeted by 2028-29; state-wise annexure published [11]
Cost escalation Fact

The sanctioned cost of the awarded length was ₹32.17 crore/km against ₹15.37 crore/km approved — 158% of the 2017 estimate (Mar 2023). [6]

Logistics parks not delivered Fact

None of the 35 planned multimodal logistics parks had been developed by March 2023. [6]

Port access lagged Fact

Coastal & port connectivity roads were 5.2% complete in March 2023 — the weakest component. [6]

What replaced Phase-I awarding Fact

New Phase-I sanctions have been discontinued since November 2023. New national-highway projects continue via standalone approvals — e.g. the CCEA approved the Rameshwar–Paradeep coastal highway (Rs 8,300.79 crore, HAM) in June 2026 without a Bharatmala Phase-II classification. No successor framework is captured here. [7][30]

Data gaps

What this page does not yet know

Sources

Source record

Data as of 22 Jul 2026 · verified 9 Oct 2026. Numbers in brackets throughout the page refer to this list.

  1. [1]Ahmedabad–Dholera Expressway is bringing cities, families & dreams closer ↗PIB (Ministry of Road Transport & Highways) · 2026-02-27 · government · confidence high
  2. [2]Cabinet approves one new project covering Ahmedabad District in the state of Gujarat, increasing the existing network of Indian Railways by about 134 Kms ↗PIB (Cabinet / Ministry of Railways) · 2026-05-13 · government · confidence high
  3. [3]Dholera Airport 80% complete; operations eyed by October ↗Whalesbook · 2026-07-15 · trade press · confidence low
  4. [4]Fujifilm and Tata Electronics sign MoU for semiconductor materials plant in Dholera ↗FUJIFILM Holdings · 2026-09-17 · company · confidence high
  5. [5]Lok Sabha Unstarred Question No. 1077 — Bharatmala Pariyojana ↗Lok Sabha (MoRTH reply) · 2018-02-08 · government · confidence high
  6. [6]Public Accounts Committee (2023-24), 144th Report — Implementation of Phase-I of Bharatmala Pariyojana ↗Lok Sabha Secretariat · 2024-04-29 · government · confidence high
  7. [7]Over 22,700 km of roads completed under Bharatmala Pariyojana, government tells Parliament ↗Swarajya · 2026-07-23 · trade press · confidence medium
  8. [8]Building Bharat — Powering infrastructure through Make in India ↗PIB / Ministry of Information & Broadcasting · 2025-04-01 · government · confidence high
  9. [9]Bengaluru–Chennai Expressway to boost connectivity to key industrial, logistics hubs: FM Sitharaman ↗IANS (via SocialNews.XYZ) · 2026-06-14 · trade press · confidence medium
  10. [10]Sagarmala: Transforming India's maritime landscape ↗PIB · 2026-04-11 · government · confidence high
  11. [11]Rajya Sabha Unstarred Question 414 — Implementation of Bharatmala Pariyojana (answer + state-wise annexure) ↗Ministry of Road Transport and Highways (via Rajya Sabha Secretariat) · 2026-07-22 · government · confidence high
  12. [12]Highways Transformation: Powering India's Journey Towards Viksit Bharat ↗PIB (Ministry of Road Transport & Highways) · 2026-06-14 · government · confidence high
  13. [13]Turning Struggles into Strength: The Human Impact of Raipur-Vizag Corridor ↗PIB (Ministry of Road Transport & Highways) · 2025-12-07 · government · confidence high
  14. [14]Bharatmala — Wikipedia (Phase-I economic-corridor list) ↗Wikipedia · undated · reference · confidence medium
  15. [15]NHIDCL Ongoing Projects — status per Bharatmala Pariyojana (as on 30.04.2026) ↗National Highways and Infrastructure Development Corporation Limited · 2026-05 · psu · confidence high
  16. [16]Zojila Tunnel Project ↗PIB (Ministry of Road Transport & Highways) · 2024-08-08 · government · confidence high
  17. [17]Zojila Tunnel Breakthrough: MEIL Group Creates History in the Himalayas ↗Megha Engineering & Infrastructures Limited (MEIL) · 2026-06-09 · company · confidence high
  18. [18]Breakthrough achieved in Zojila Tunnel, likely to open for public in 2028 ↗Business Standard · 2026-06-09 · trade press · confidence medium
  19. [19]Gadkari Reviews Progress of India's first Grade-Separated Urban Expressway (Dwarka Expressway) ↗PIB (Ministry of Road Transport & Highways) · 2021-03-04 · government · confidence high
  20. [20]PM inaugurates 19 km long Haryana Section of Dwarka Expressway ↗PIB (Prime Minister's Office) · 2024-03-11 · government · confidence high
  21. [21]PM lays foundation stone and dedicates to nation development projects worth over Rs 24,300 crore in Bikaner, Rajasthan (dedicates six-lane Greenfield Expressway section of the Amritsar-Jamnagar Economic Corridor) ↗PIB (Prime Minister's Office) · 2023-07-08 · government · confidence high
  22. [22]Amritsar-Jamnagar Expressway — Wikipedia ↗Wikipedia · undated · reference · confidence medium
  23. [23]PM Modi to dedicate Delhi-Amritsar-Katra Expressway today ↗DD News (Prasar Bharati) · 2026-07-17 · government agency · confidence high
  24. [24]PM Modi Inaugurates Delhi-Amritsar-Katra Expressway ↗NDTV · 2026-07-17 · trade press · confidence medium
  25. [25]Delhi-Amritsar-Katra Expressway — Wikipedia ↗Wikipedia · undated · reference · confidence medium
  26. [26]Everything You Wanted To Know About The 262-km Greenfield Chennai-Bengaluru Expressway ↗India Infra Hub · 2020-02-02 · trade press · confidence medium
  27. [27]Delhi-Mumbai Expressway In Charts: package and contractor split ↗India Infra Hub · undated · trade press · confidence medium
  28. [28]Delhi-Mumbai Expressway — Package Level Status (November 2022) ↗National Highways Authority of India · 2022-11-10 · psu · confidence medium
  29. [29]Delhi-Mumbai Expressway Full Completion Date Announced ↗Magicbricks (reporting the Road Transport Minister) · 2026-07-09 · trade press · confidence medium
  30. [30]NHAI Receives Overwhelming Response from Bidders for Construction of Coastal Corridor from Rameshwar to Paradeep in Odisha ↗PIB (Ministry of Road Transport & Highways) · 2026-09-01 · government · confidence high
Method

How this page is built

Facts and headline metrics come from the SID logistics reference layer and the shared Techadyant source registry; every figure carries a date and a numbered source. The Techadyant reading — why it matters, consequences, opportunity surfaces — is labelled as analysis.

Connected projects, industrial nodes, opportunities, signals and reports are not hand-listed. They are derived at build time from evidenced links in the Atlas graph, so a new project, signal or report linked to Bharatmala appears here on the next build. We don’t replicate India’s infrastructure databases. We interpret them.