Only figures with a source on file. Each carries its own date — programme figures are published at different times, so they are not summed or compared across dates.
Completion targetProjects targeted for completion by 2028-2922 Jul 2026 [11]
Completed
Constructed13,499 km (Mar 2023) → 19,826 km (Feb 2025) → 22,709 km (May 2026)31 May 2026 [6][8][7]
Greenfield high-speed corridors6,669 km awarded · 4,610 km completed28 Feb 2025 [8]
Operational
—
02 · Why it mattersTechadyant analysis
How Bharatmala is changing India’s industrial system
Interpretation, labelled. Sourced statements are marked Fact.
Analysis Bharatmala matters less for the kilometres it adds than for how it chose them: by corridor, along origin–destination freight routes. Corridors change which industrial locations are cheap to reach, and so where new capacity is likely to go.
Fact In practice it became an expressway programme. By March 2023, greenfield expressways were 302.75% awarded and 119.75% completed against their approved length, while coastal and port connectivity roads were 20.75% awarded and 5.2% completed. [6]
Fact The node-level effect is visible at Dholera: the 109 km NE-8 expressway, built under Bharatmala, cut Ahmedabad–Dholera travel from 2 h 15 min to 45 min when it opened for testing in Feb 2026. [1]
Fact Execution is now a finishing problem with a map: 22,709 of 26,425 awarded km were built by May 2026, but the remainder is uneven — Punjab (672 km under construction), Andhra Pradesh (382), Karnataka (334) and Uttar Pradesh (299) hold the largest pending stretches, and the completion target has moved to 2028-29. [11]
Analysis Where the pending kilometres sit is where freight gains stay locked: a corridor that is open in one state and stuck in the next delivers a fraction of its end-to-end economics, so state-level delivery speed has become the binding variable for industrial connectivity.
03 · Geographic footprintDerived from the graph
Where Bharatmala meets India’s industrial geography
Shows only industrial nodes and infrastructure reached through an evidenced project link, not the programme’s full national network. Techadyant does not replicate PM GatiShakti’s GIS. National footprint: national highway network — economic, inter-corridor, feeder, border and port-connectivity routes. The linked roads follow NHAI’s own Bharatmala map, and the toggles add its wider network (expressways, economic and national corridors, inter-corridor and feeder roads). That map is marked not to scale, so every line is schematic: it shows where a corridor runs, not its surveyed alignment.
Industrial node · Gujarat
Dholera
India’s only approved commercial logic fab sits in a node whose road link has arrived, whose airport is close, and whose rail link is five years out. ICS: 55 (Moderate).
05 · Connected industrial nodesDerived from the graph
Industrial nodes affected
Each card shows the evidence path from programme to node. A node appears only when a sourced project links them; two locations being close is not enough.
India’s densest electronics-assembly belt sits within ~50 km of two major ports and an international cargo airport — the test of whether gateway proximity is already priced in.
06 · Connected logistics systemDerived from the graph
The connected logistics system
Road → rail → DFC → logistics parks → ports → air cargo → industrial nodes. Filled only from records linked to this programme (Atlas projects and the SID logistics layer). An empty row means no linked record yet, not that nothing exists.
Road
Ahmedabad–Dholera Greenfield Expressway (NE-8)trial · linked projectBengaluru–Chennai Expresswayunder construction · linked projectDelhi–Mumbai Expressway (Delhi–Vadodara–Mumbai Greenfield Expressway)under construction · linked projectDelhi–Mumbai Expressway JNPT spur (Package 13)under construction · linked projectDelhi–Amritsar–Katra Expresswayunder construction · linked projectAmritsar–Jamnagar Expressway (Economic Corridor EC-3)under construction · linked projectRaipur–Visakhapatnam Economic Corridor (NH-130CD, EC-15)under construction · linked projectDwarka Expressway (Delhi–Gurugram elevated urban expressway)operational · linked projectZojila Tunnel (NH-1 Srinagar–Leh)under construction · linked projectBharatmala Pariyojana road network (Phase-I aggregate)reference record · SID logistics layer
Each statement is tagged Fact (sourced) or Analysis (Techadyant interpretation).
Manufacturing
Corridors reprice industrial locations
Fact NE-8 cut Ahmedabad–Dholera travel time from 2 h 15 min to 45 min (Feb 2026). [1]
Analysis For a greenfield node, the first fast road link is often what makes construction, workforce and early logistics practical before rail arrives.
Logistics
Trunk speed improved faster than the first and last mile
Fact Expressways over-delivered while MMLPs (0 of 35) and port-connectivity roads (5.2%) lagged as of Mar 2023. [6]
Analysis Freight gains on the trunk can be absorbed at port gates and consolidation points that the programme did not build.
Fact The Delhi–Mumbai Expressway — 1,386 km, ~Rs 1 lakh crore, ~80% complete (Jul 2026) — includes a dedicated ~3 km spur to Jawaharlal Nehru Port (Package 13). [12][28]
Analysis A trunk this fast shifts the bottleneck to interchanges and city gates, which is where consolidation capacity — not haulage — captures the gain.
Trade
Export gateways were the weak link
Fact Coastal & port connectivity was 20.75% awarded and 5.2% completed (Mar 2023). [6]
Analysis The port leg is now addressed partly through Sagarmala’s port-connectivity pillar, so gateway access depends on two programmes.
Fact PIB describes the Raipur–Visakhapatnam corridor (EC-15) as directly linked to Visakhapatnam Port and the Chennai–Kolkata NH, with “improved connectivity to ports and industrial hubs, quicker exports, smoother supply chains”. [13]
Analysis Interior mineral and steel belts that gain a designed port axis may find export logistics materially cheaper once the corridor opens (targeted December 2026).
Regional development
Corridor alignment follows industrial corridors
Fact The Bengaluru–Chennai Expressway, built under Bharatmala Phase-I, is described as a priority corridor of the Chennai–Bengaluru Industrial Corridor, with industrial areas and a proposed MMLP on its Karnataka section. [9]
Analysis Where highway and industrial-corridor planning coincide, the highway becomes the corridor’s spine — the pattern to watch at other NICDP nodes.
Fact The 13.153 km Zojila tunnel, listed by NHIDCL under Bharatmala works, achieved breakthrough in June 2026 — the border component’s flagship move toward an all-weather Srinagar–Leh axis (reported opening target February 2028). [17][15][18]
Supply chains
Road remains the default mode for time-sensitive inputs
Analysis Faster corridors make road more competitive against rail for components and finished goods even as the DFC opens. That may slow the modal shift the freight corridors were built for.
Components and materials move by road over economic and feeder corridors. Analysis
Manufacturing node
Industrial nodes gain fast road access — e.g. Dholera via NE-8. Fact[1]
Freight network
22,709 km of Phase-I corridors constructed (May 2026). Fact[7]
Logistics node
The 35 planned MMLPs had not been developed as of Mar 2023 — the missing consolidation layer. Fact[6]
Port / airport
Port connectivity roads were 5.2% complete (Mar 2023); the Delhi–Mumbai Expressway adds a dedicated JNPT spur (Package 13) and PIB ties EC-15 directly to Visakhapatnam Port. Fact[6][28][13]
Market
Domestic markets gain most directly; export gains depend on the port leg. Analysis
09 · Opportunity surfacesOpportunity surface
Where new opportunity may appear
Analytical hypotheses with a sourced trigger, stated constraints and a confidence label (High / Medium / Emerging). Not forecasts, and not procurement signals.
Opportunity surfaceConfidence: Medium
Road-bridged materials and gas logistics for the Dholera fab before rail arrives (2026–2031)
Trigger
The NE-8 expressway is open for testing while the Sarkhej–Dholera rail line is approved only for completion by 2030-31; Fujifilm has signed an MoU for a phased materials plant inside the SIR. [1][2][4]
Industrial effect
For roughly five years every bulk chemical, gas cylinder and tool spare reaches the fab by road, over ~160–260 km (straight-line) from Gujarat’s ports. Fab ramp-up depends on dependable, contamination-controlled road logistics for hazardous and high-purity inputs. Materials makers (Fujifilm MoU) and gas suppliers locating inside the SIR shorten the most fragile inbound legs. Import dependence on photoresists, slurries and high-purity chemicals persists, but the physical exposure moves from long road hauls to on-site supply.
Potential opportunity
Potential demand for hazmat-certified, high-purity chemical and gas logistics, on-site storage and cylinder/ISO-tank management serving the fab and its vendor park during the pre-rail window.
Affected sectors
Electronic materials · Specialty gases
Constraints
Fab production timeline could slip, delaying demand.
Tata and global gas/chemical majors may run captive logistics, leaving little room for third parties.
Vendor-park and materials MoUs may not convert to builds.
Via Ahmedabad–Dholera Greenfield Expressway (NE-8) · horizon near · a hypothesis, not a forecast or procurement signal.
Opportunity surfaceConfidence: Emerging
Fab-grade air-cargo handling at Dholera’s new airport
Trigger
Dholera International Airport is under construction next to the SIR, with a planned 2,500 sq m cargo hub and a direct expressway interchange. [3][1]
Industrial effect
Time-critical shipments could shift from Ahmedabad (~105 km straight-line) to an on-site airport. Wafer, spare-part and specialty-material movements would be faster and handled closer to the cleanroom. A small general-purpose cargo hub may not meet semiconductor needs (ESD, vibration, temperature, bonded clearance).
Potential opportunity
Potential opening for semiconductor-specialised air-cargo handling, bonded storage and customs-brokerage capability sized to the fab rather than to general cargo.
Affected sectors
—
Constraints
Airport opening date and cargo-terminal scope are single-source and unconfirmed.
Air-freight volumes depend on fab ramp; Ahmedabad may remain the default gateway.
Via Ahmedabad–Dholera Greenfield Expressway (NE-8) · horizon medium · a hypothesis, not a forecast or procurement signal.
Opportunity surfaceConfidence: Emerging
Port-access roads and logistics parks — the parts of Bharatmala Phase-I that lagged
Trigger
Parliament’s Public Accounts Committee (Apr 2024, on CAG audit data to Mar 2023) found coastal & port connectivity roads only 5.2% completed and none of 35 planned multimodal logistics parks developed, while the highway corridors raced ahead. New Phase-I sanctions have been discontinued since Nov 2023. [6][7]
Industrial effect
Freight gains on the trunk can be absorbed at the port gate and the first/last mile. Export-oriented clusters near ports may see trunk-route gains without matching gateway gains.
Potential opportunity
Port-access, consolidation and logistics-park capacity — public or private — could fill the gap the programme left, under whichever successor framework funds it.
Affected sectors
Logistics · Port-linked manufacturing
Constraints
The PAC findings are dated March 2023; some MMLPs and port links may have progressed since — current status is not captured here.
Successor funding framework for new highway sanctions is not documented in this layer.
Port-connectivity works are also funded under Sagarmala, so the gap may be filled there.
Triggered by this programme · horizon medium · a hypothesis, not a forecast or procurement signal.
Opportunity surfaceConfidence: Medium
Warehousing and distribution consolidation along the Delhi–Mumbai Expressway
Trigger
The 1,386 km, ~Rs 1 lakh crore Delhi–Mumbai Expressway is ~80% complete (Jul 2026) with full completion signalled within two years, and delivers a dedicated ~3 km spur to Jawaharlal Nehru Port (Package 13). [29][28]
Industrial effect
Interchange locations along Rajasthan, Madhya Pradesh and Gujarat become the natural points where North–South freight consolidates or breaks bulk, cutting drayage into the trunk. Distribution-intensive industries (consumer goods, electronics, auto components) could re-site regional warehouses from city edges to expressway interchanges.
Potential opportunity
Warehouse parks, 3PL consolidation hubs and truck-support services at DME interchanges — private or PPP — could capture the modal shift; the operator ecosystem (e.g. national logistics-park developers) is already positioned along the axis.
Affected sectors
Logistics · Warehousing · Third-party distribution
Constraints
Multimodal Logistics Parks planned under the programme were not developed as of Mar 2023, so the public consolidation layer is missing — private facilities would fill that role.
Land assembly and state-level warehousing policy along the alignment vary.
Toll pricing and the pace of the final Gujarat/Maharashtra sections affect the traffic ramp.
Triggered by this programme · horizon medium · a hypothesis, not a forecast or procurement signal.
Opportunity surfaceConfidence: Medium
Mineral-belt export logistics via the Raipur–Visakhapatnam corridor
Trigger
The 465 km, Rs 16,482 crore Raipur–Visakhapatnam Economic Corridor (NH-130CD) is expected to complete by December 2026 and, per PIB, will be "directly linked to the Visakhapatnam Port and the Chennai-Kolkata National Highway" with "improved connectivity to ports and industrial hubs, quicker exports, smoother supply chains". [13]
Industrial effect
Mine, plant and industrial-hub traffic in the belt gains a designed port axis for the first time, replacing mixed-traffic state-road routings. Steel, cement, aluminium and mineral exporters in the belt may find port-gate logistics materially cheaper and more predictable, strengthening the case for downstream processing at interior plants.
Potential opportunity
Freight forwarding, rakes-to-road transloading, port-yard capacity and industrial last-mile services along the corridor could grow with the export flow once the corridor opens.
Affected sectors
Mining & metals · Port logistics · Steel
Constraints
Completion date (Dec 2026) is a target from a Dec 2025 release; slippage is possible.
Freight volumes are not published here — no market size is implied.
Rail (DFC feeder and IR lines) competes for the same mineral flows.
Triggered by this programme · horizon near · a hypothesis, not a forecast or procurement signal.
Opportunity surfaceConfidence: Emerging
All-weather Ladakh logistics once the Zojila tunnel opens
Trigger
The 13.153 km Zojila tunnel — listed by NHIDCL under Bharatmala Pariyojana works — achieved final breakthrough on 9 Jun 2026; opening is reported to be targeted around February 2028. [15][17][18]
Industrial effect
Srinagar–Leh road access becomes year-round, ending the winter window in which the region is effectively road-isolated. Supply chains serving Ladakh — provisions, construction materials, tourism services — could shift from stockpiling to scheduled replenishment; tourism season may lengthen.
Potential opportunity
Scheduled trucking services, winter-grade warehousing and tourism logistics on the axis could emerge once the tunnel opens.
Affected sectors
Border logistics · Tourism · Regional supply
Constraints
Opening target (Feb 2028) is a press-reported estimate; finishing works at altitude have slipped before.
This layer records publicly documented infrastructure only; no operational or defence logistics detail is included.
Air cargo (Leh) will keep carrying the highest-value flows.
Triggered by this programme · horizon long · a hypothesis, not a forecast or procurement signal.
Programme scorecard (industrial connectivity, supply-chain impact, strategic importance, opportunity potential): not published. Techadyant shows a score only once its methodology is documented and the inputs exist — see the node-level methodology.
10 · Related projectsFact
Projects linked to the programme
Projects in the Atlas that carry a sourced link to this programme. New linked projects appear here automatically.
under constructionDescribed as being developed under Bharatmala Pariyojana Phase-I (Jun 2026); construction progress and opening date not stated. Alignment begins at Hoskote (Karnataka) and ends at Sriperumbudur (Tamil Nadu), with last-mile to Chennai via two elevated connectors.
under construction~80% complete per the Road Transport Minister (Jul 2026), with full completion signalled within two years. Sections opened progressively since Feb 2023.
₹1.00 lakh cr
G R Infraprojects Ltd — EPC/HAM contractor (8 packages (~290 km); corridor package total disputed — 52 per undated trade press vs 53–54 in parliamentary replies) [27]H G Infra Engineering — EPC contractor (package award holder) [27]
under constructionRajasthan section (>500 km) dedicated 8 Jul 2023; a further 27.1 km Deogarh–Gujarat border stretch opened Sep 2026; remaining sections under construction.
Contractors are listed only where a source names them on this project — never inferred from sector or geography. “Not documented” means no source on file yet, not that none exists.
11 · Geographic coverageFact
State-wise coverage matrix
Reproduced from a single dated primary source at one reporting date. Columns are the programme’s own published categories — they are state programme totals, not attributable to a single scheme, and are not summed with figures from other dates. Rows are as published, including any cross-footing artefacts.
State / UT
Total (km)
Awarded (km)
Constructed (km)
Under construction (km)
Andhra Pradesh
2,525
1,936
1,554
382
Assam
433
431
414
17
Bihar
1,572
1,159
815
344
Chhattisgarh
571
471
422
49
Delhi
203
203
195
8
Goa
26
26
26
0
Gujarat
1,577
1,194
1,068
126
Haryana
1,058
1,058
1,011
47
Himachal Pradesh
167
167
117
50
Jammu & Kashmir
433
251
179
72
Jharkhand
1,000
801
557
244
Karnataka
2,059
1,603
1,269
334
Kerala
1,126
708
584
124
Madhya Pradesh
3,063
2,017
1,826
191
Maharashtra
3,029
2,174
2,000
174
Manipur
635
635
570
65
Meghalaya
170
170
153
17
Mizoram
593
593
542
51
Nagaland
208
208
168
40
Odisha
1,586
967
948
19
Punjab
1,764
1,553
881
672
Rajasthan
2,503
2,360
2,264
96
Tamil Nadu
2,414
1,476
1,357
119
Telangana
1,719
1,026
955
71
Tripura
94
94
69
25
Uttar Pradesh
3,126
2,495
2,196
299
Uttarakhand
273
264
204
60
West Bengal
874
385
364
21
Total
34,800
26,425
22,709
3,716
State-wise Bharatmala Pariyojana lengths from the Rajya Sabha annexure (22 Jul 2026). Columns are state totals for the whole programme — lengths under different national-highway schemes are not separable at this resolution. Transcription note: state figures are reproduced exactly as published and do not cross-foot perfectly to the declared national totals (states sum to 34,801 total / 22,708 constructed / 3,717 under construction against the declared 34,800 / 22,709 / 3,716) — a rounding artefact in the annexure itself; the awarded column cross-foots exactly. [11]
Bharatmala complementsSagarmala ProgrammeBoth fund port connectivity: Bharatmala’s coastal & port roads and Sagarmala’s port-connectivity pillar. [5][10]
Bharatmala complementsMultimodal Logistics Parks (MMLPs)Logistics reference layerMMLPs were planned under the Bharatmala umbrella; none developed by Mar 2023. [6]
14 · Related signals
Latest Bharatmala signals
Surfaced automatically when a Signal names the programme, is linked to it by Techadyant, or covers a node or project it reaches. The reason is shown on each card.
Linde India has secured a land parcel in Sanand, Gujarat, for a semiconductor packaging-gas facility - its second India chip-gas site after the Dholera plant set to supply Tata''s fab. Electronic specialty gases are a real, under-noticed chip dependency; the supply is being localised, but largely by global majors - which brings the molecule onshore without yet localising the technology or the ownership.
Why it is here: On Dholera, a node this programme reaches
At SEMICON India 2026, Tata Electronics signed MoUs to build a 363-acre vendor park around its Dholera fab (with Ascendas First Space) and to localise critical inputs - Fujifilm's roughly Rs 800 crore materials plant, JSR's photoresists and chemicals, plus Nexperia, BESI and SCL. It is the first concrete attempt to populate the supplier layer that has to sit around India's largest silicon project.
Why it is here: On Dholera, a node this programme reaches
Dholera's industrial ambition rests on a single water artery. The fab can be financed and built on schedule; the water to run it at full utilisation has to arrive every day through the Narmada canal — and that concentration, not land or capital, is the binding constraint.
Why it is here: On Dholera, a node this programme reaches
Of a ₹91,000 crore mature-node fab, roughly two-thirds flows to ASML, AMAT, Lam, TEL and KLA. The Indian-capture economy lives in the remaining one-third — construction, gases, UPW, logistics and the durable industrial capabilities those build.
Why it is here: On Dholera, a node this programme reaches
First 157.92 km of the Delhi–Amritsar–Katra Expressway dedicated (Packages 1–5, ~Rs 9,680 crore) [23]
Rajya Sabha reply: completion targeted by 2028-29; state-wise annexure published [11]
Cost escalation Fact
The sanctioned cost of the awarded length was ₹32.17 crore/km against ₹15.37 crore/km approved — 158% of the 2017 estimate (Mar 2023). [6]
Logistics parks not delivered Fact
None of the 35 planned multimodal logistics parks had been developed by March 2023. [6]
Port access lagged Fact
Coastal & port connectivity roads were 5.2% complete in March 2023 — the weakest component. [6]
What replaced Phase-I awarding Fact
New Phase-I sanctions have been discontinued since November 2023. New national-highway projects continue via standalone approvals — e.g. the CCEA approved the Rameshwar–Paradeep coastal highway (Rs 8,300.79 crore, HAM) in June 2026 without a Bharatmala Phase-II classification. No successor framework is captured here. [7][30]
Data gaps
What this page does not yet know
Component-wise progress after March 2023 is not captured.
Package-level project inventory (MoRTH/NHAI sanction and award records) is not yet built into the Atlas; the state-wise matrix is the finest geographic resolution carried here.
The successor framework for new highway sanctions after Phase-I is not formally documented; standalone CCEA approvals (e.g. Rameshwar–Paradeep, Jun 2026) are the observed pattern.
A proposed Phase-II (48,877 km) appears in secondary coverage; no formal approval is captured, so it is not treated as an approved programme here.
Corridor alignments are not mapped; the footprint shows only projects linked to this Atlas’s nodes.
Completion target is unreconciled: the Jul-2026 Rajya Sabha reply recorded here gives 2028-29, while a PRS analysis of the 2026-27 budget (Mar 2026) carries a revised deadline of 2027-28. Both are retained as reported; the later date is shown in the glance row.
Expenditure of Rs 5,63,779 crore to 30.06.2026 and the 2028-29 completion target rest solely on the Rajya Sabha AU414 annexure. The PDF was captured during research but could not be independently re-retrieved on 2026-10-11 (sansad.in returned no content), and neither figure appears in secondary coverage. Treat as single-source pending re-capture.
Sources
Source record
Data as of 22 Jul 2026 · verified 9 Oct 2026. Numbers in brackets throughout the page refer to this list.
Facts and headline metrics come from the SID logistics reference layer and the shared Techadyant source registry; every figure carries a date and a numbered source. The Techadyant reading — why it matters, consequences, opportunity surfaces — is labelled as analysis.
Connected projects, industrial nodes, opportunities, signals and reports are not hand-listed. They are derived at build time from evidenced links in the Atlas graph, so a new project, signal or report linked to Bharatmala appears here on the next build. We don’t replicate India’s infrastructure databases. We interpret them.