Nexon Geochem Signs Rs 1,250 Crore NdFeB Magnet MoU With Andhra Pradesh: A Named Investor Behind the State's Minerals Push
- Nexon Geochem signed an MoU with the Andhra Pradesh Economic Development Board on 14 October for a sintered NdFeB magnet facility at Thondangi, Kakinada.
- The investment is Rs 1,250 crore in two phases (Rs 750 crore and Rs 500 crore) for 600 tonnes a year of planned capacity.
- The MoU is a project-formation step; no construction start, timeline, feedstock source or offtake has been disclosed.
- It follows Nexon's July technology MoU with Russia's Giredmet; the reports do not link the two or reconcile the 600-tonne and 1,200-tonne figures.
- The real tests are approvals, financial close, feedstock and qualified first output.
- Nexon Geochem signed an MoU with the Andhra Pradesh Economic Development Board on 14 October for a sintered NdFeB magnet facility at Thondangi, Kakinada.
- The investment is Rs 1,250 crore in two phases (Rs 750 crore and Rs 500 crore) for 600 tonnes a year of planned capacity.
- The MoU is a project-formation step; no construction start, timeline, feedstock source or offtake has been disclosed.
- It follows Nexon's July technology MoU with Russia's Giredmet; the reports do not link the two or reconcile the 600-tonne and 1,200-tonne figures.
- The real tests are approvals, financial close, feedstock and qualified first output.
- Business Standard (14 Oct 2026): https://www.business-standard.com/industry/news/nexon-geochem-to-set-up-1-250-crore-rare-earth-magnet-plant-in-andhra-126101400554_1.html
- Deccan Chronicle (14 Oct 2026): https://www.deccanchronicle.com/southern-states/andhra-pradesh/hyderabad-nexon-geochem-to-set-up-rare-earth-permanent-magnet-facility-in-andhra-pradesh-1995765
- Autocar Professional (15 Jul 2026): https://www.autocarpro.in/news/nexon-geochem-partners-with-russias-giredmet-on-rare-earth-magnets-133602
The MoU
On 14 October Nexon Geochem announced that it has signed a Memorandum of Understanding with the Andhra Pradesh Economic Development Board (APEDB) for an integrated sintered neodymium-iron-boron (NdFeB) permanent-magnet facility at Thondangi in Kakinada district, within the Kakinada SEZ.
- Investment: Rs 1,250 crore in total, split into Rs 750 crore for the first phase and Rs 500 crore for the second.
- Capacity: 600 tonnes of permanent magnets a year. The reports do not say how capacity is divided between the phases.
- Markets: electric vehicles, wind turbines, industrial automation and defence, with the stated aim of reducing import dependence.
- Status: the MoU is signed and the facility 'will be set up'. No construction start, completion date or phase timeline has been given.
The company's director, Praveen Kumar Choudhary, describes the aim as an 'integrated NdFeB magnet manufacturing ecosystem'. The reports use 'integrated' without defining which stages (oxide-to-metal, alloying, powder, sintering, finishing) the site will include.
How it fits Nexon's earlier plans
In July, Nexon Geochem signed a technology-transfer MoU with Giredmet, a Rosatom-linked Russian research institute, and spoke of a fully integrated magnet platform targeting 1,200 tonnes a year by FY2033, with an initial facility planned in Hyderabad. The new MoU puts a state agency, a site and a capital plan behind the company's ambition. The reports we read do not say how the 600-tonne Kakinada plan relates to the earlier 1,200-tonne target, or whether Giredmet's technology will be used.
Why it matters
India's rare-earth problem is not only ore. The chain from separated oxides and metals to finished magnets is where most capacity is missing, and sintered NdFeB magnets are a chokepoint for EV motors, wind generators and several defence systems. Our earlier signal on India's four planned critical-mineral processing parks (S-096) treated the Andhra Pradesh park as infrastructure intent. A named investor, site and capital plan is a concrete step beyond that, though it is a separate project agreement and not proof the park is moving.
What the MoU does not establish
An MoU is not an approval, a financial close or a construction start. The reports do not name the source of the rare-earth oxide feedstock, the heavy-rare-earth strategy, offtake customers or the expected domestic content. If feedstock is imported, the plant would still add downstream capacity but would not close the upstream chokepoint on its own.
The Techadyant view
This is a useful but early signal. It shows capital and state support gathering around a downstream magnet node, which is the layer India most lacks. The real thresholds are land and approvals, financial close, a defined technology route, feedstock contracts and qualified first output.
What to watch next
Watch for land allotment and environmental approvals, financial close, the technology partner and process route, feedstock and heavy-rare-earth sourcing, first pilot output, and customer or defence qualification.
Track the systems we watch
Signals, reports and briefings on India’s industrial transformation.
Related research
Magnet-Free Motors Could Redraw India's Rare-Earth Value Chain
Read →Battery Materials Processing — Lithium, Cobalt, Nickel and the Cell-Ecosystem Opportunity
Read →The Refinery Equipment and Technology-Transfer Layer Beneath Mineral Processing
Read →